Skip to main content

State Significant Development

Determination

Crows Nest OSD Site C - Stage 2

North Sydney

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Design and construction of a nine storey commercial building at Crows Nest OSD Site C

Consolidated Consent

Consolidated consent after MOD 2

Archive

Notice of Exhibition (1)

EIS (23)

Response to Submissions (6)

Additional Information (1)

Determination (4)

Post-determination Notices (1)

Approved Documents

Management Plans and Strategies (10)

Reports (1)

Other Documents (25)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

There are no inspections for this project.

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 12 of 12 submissions
WaterNSW
Comment
PARRAMATTA , New South Wales
Message
Thank you for requesting WaterNSW's comments on the EIS for the Sydney Metro Crows Nest OSD Site C - Stage 2. Please note that as the subject site is not located in close proximity to any WaterNSW land or assets, and as an SSD any flood works or licensing approvals will be assessed by others, the risk to water quality is considered to be low and WaterNSW has no comments or particular requirements.
Reginald Cattlin
Comment
WOLLSTONECRAFT , New South Wales
Message
I attended the Community Information session on 19 June at the Crow's Nest Centre, just as well I'm familiar with the centre as I did not see any directions at the entrance to the downstairs room.
In considering the several sites I find Site C an architecturally uninspiring building. I doubt if it will be compatible with surrounding buildings and add any aesthetic value to the area. In addition I also doubt it will be in symmetry with surrounding buildings when, or if, they are constructed. In my opinion that site would be better left as an open space to transition to the proposed park opposite as there is a desperate lack of open space for residents and workers in the surrounding area. I realise that site includes an entrance/exit to the Metro station but I think a more creative building could be installed.
As for Site B I can see the value of a boutique hotel for the area or a residential block of limited height taking into account overshadowing of the area east and west. Regarding Site C I have already commented previously on the opportunistic ill considered original proposal. The drawing in the brochure is an improvement but I still think a building of that size will only add to the over development of the Crow's Nest-St Leonards area resulting in many vacant residential units for years to come.
Heritage NSW – HERITAGE COUNCIL OF NSW
Comment
PARRAMATTA , New South Wales
Message
Heritage Council of NSW comments attached.
Attachments
North Sydney Council
Comment
NORTH SYDNEY , New South Wales
Message
North Sydney Comment - Metro Crows Nest Site C/ OSD
To whom it may concern,
Council notes the building design and project scope of this proposal and raises no objection. The proposal is premised on the previous concept approval and the Design Excellence process required by the North Sydney LEP.
With respect to the broader design of the Metro site, Council maintains its previously stated concerns regarding final traffic flows and public domain issues.

Regards
Gavin McConnell
Executive Planning Advisor
ROADS AND MARITIME SERVICES DIVISION
Comment
PARRAMATTA , New South Wales
Message
Hi Joina,
TfNSW will not provide a response on this application.
TfNSW internal stakeholder comments have been provided directly to Sydney Metro project team.
Regards
Zhaleh
TRANSPORT FOR NSW
Comment
Chippendale , New South Wales
Message
TfNSW will not provide a response to DPIE for the subject development application as this development application is from one of the transport cluster agency (Sydney Metro).
john fitzgerald
Object
Crows Nest , New South Wales
Message
Please see attachment
Attachments
ENVIRONMENT PROTECTION AUTHORITY
Comment
Sydney , New South Wales
Message
Please see attached
Attachments
Biodiversity and Conservation Division
Comment
PARRAMATTA , New South Wales
Message
Please find attached EES response
Attachments
Fire and Rescue NSW
Comment
,
Message
Dear Joina,

Notice of Exhibition
Sydney Metro Crows Nest OSD Site C - Stage 2 (SSD-13852803)

Thank you for notifying Fire and Rescue NSW (FRNSW) of the exhibition of the Environmental Impact Statement (EIS) for the above State Significant Development project.

It is understood that the EIS has been prepared by Kate Tudehope and Anna Nowland of Ethos Urban on behalf of Sydney Metro (the Applicant) to address matters identified in the relevant Secretary’s Environmental Assessment Requirements (SEARs). These matters are in relation to the design, construction, and operation of a commercial office building (the Development) over Sydney Metro’s Crows Nest Station.

The following comments are submitted for consideration following a review of relevant parts of the EIS and associated appendices.

It is noted that an application for a Crown Certificate will be made for the Development under the applicable legislative provisions of the NSW Environmental Planning and Assessment Act 1979, such that there would be no requirement for the Applicant (or representatives thereof) to make required formal submissions in accordance with Part 8, Division 2, Clause 144 of the NSW Environmental Planning and Assessment Regulation 2000. Such submissions are essential in ensuring that the fire and life safety measures afforded to a development are not only adequate to meet the extent of potential incidents, but suitably accommodate the operational requirements of attending firefighters in undertaking intervention activities. To ensure that suitable consideration in given to these requirements, FRNSW recommend that the following conditions be included in the relevant instrument of consent should the Development be granted approval.

1. Should the fire engineering design be reliant upon performance solutions to achieve compliance with the performance requirements of the National Construction Code (NCC), the Applicant (or representative thereof) be required to consult with FRNSW by way of the Fire Engineering Brief Questionnaire (FEBQ) process.
2. A Fire Engineering Report (FER) be prepared by the Applicant (or representatives thereof) and submitted to FRNSW for review and comment.

The above recommendations reflect the consultation and approval process that would be otherwise followed should the Development not have been seeking to make application for a Crown Certificate.

If you have any queries regarding the above please contact the Fire Safety Infrastructure Liaison Unit, referencing FRNSW file number BFS21/2057. Please ensure that all correspondence in relation to this matter is submitted electronically to [email protected].

Regards,
Heritage NSW – Aboriginal cultural heritage (ACH)
Comment
Sydney , New South Wales
Message
Heritage NSW ACH Comments attached
Attachments
NSW Health Service - Health System Support Group
Comment
,
Message
No objection

Pagination

Project Details

Application Number
SSD-13852803
Assessment Type
State Significant Development
Development Type
Residential & Commercial ( Mixed use)
Local Government Areas
North Sydney
Decision
Approved
Determination Date
Decider
Director
Last Modified By
SSD-13852803-Mod-2
Last Modified On
09/10/2023

Contact Planner

Name
Paula Bizimis