CIV > $5M - Council interest
Determined
Bioenergy Facility
Northern Regional Planning Panel
Bioenergy Facility to receive STP biosolids and other organic wastes to produce compost and biogas for electricity generation
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
Determination PPSNTH-102
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
Completed declaration forms PPSNTH-102
Council Assessment Report (2)
Attachments to Council Assessment Report (6)
Attachment to assessment report
10.2021.364.1 - NRPP Report Attachment 2 - Response to Submissions Report
Attachment to assessment report
10.2021.364.1 - NRPP Report Attachment 1 - Plans
Attachment to assessment report
10.2021.364.1 - NRPP Report Attachment 4 - response to EPA
Attachment to assessment report
10.2021.364.1 - NRPP Report Attachment 3 - Elevations with height shown
Attachment to assessment report
10.2021.364.1 - NRPP Report Attachment 5 - Assessment of Submissions
Clause 4.6 variation request
M–Exception building height limit-45 Wallum Pl Byron Bay
Record of Briefing (1)
Record of Briefing
Record of Briefing PPSNTH-102
Other (3)
Links (2)
Meetings
Project Details
DA
number
10.2021.364.1
Planning panel reference number
PPSNTH-102
Capital investment value
$16,572,909
Project Address
45 Wallum Place Byron Bay 2481
Lodgement date
Referral date
Local government
Byron Shire Council
Type of matter
DA
Determination outcome
Approved
Determination Date