Project EnergyConnect (NSW - Western Section)

Development of a new 330 kV transmission line connecting the NSW and SA transmission networks (via Buronga substation) and upgrading the existing transmission line between Buronga substation and the NSW / Vic border.

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Arrange Exhibition
  4. Exhibition
  5. Collate Submissions
  6. Response to Submissions
  7. Assessment
  8. Recommendation
  9. Determination

Attachments & Resources

Notice of Exhibition (1)
Application (4)
SEARs (1)
EIS (17)
Submissions (20)
Response to Submissions (15)
Agency Advice (42)
Additional Information (5)
Determination (3)

Approved Documents

Management Plans and Strategies (2)
Other Documents (6)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

There are no inspections for this project.

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Project Details

Application Number
SSI-10040
EPBC ID Number
2020/8673
Assessment Type
State Significant Infrastructure
Development Type
Electricity supply
Local Government Areas
Wentworth Shire
Decision
Approved
Determination date
Decider
Minister

Contact Planner

Iwan Davies