Skip to main content

State Significant Development

Determination

Springvale Water Treatment Facility

Lithgow City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Consolidated Consent

Consolidated Consent

Archive

Request for SEARs (1)

SEARS (1)

EIS (20)

Response to Submissions (2)

Amendments (2)

Recommendation (8)

Determination (3)

Approved Documents

Management Plans and Strategies (13)

Reports (4)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

21/10/2020

10/05/2022

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 421 - 440 of 454 submissions
Glenys Watt
Object
Bellingen , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Glenys Watt
194 North Bank Rd
Bellingen New South Wales 2454
Sunday, October 30, 2016 - 08:07

Grant McDonald
Object
stanthorpe , Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Grant McDonald
5 Pike St
Stanthorpe Queensland 4380
Saturday, October 29, 2016 - 20:59

Kaili Leadbeatter
Object
bentley , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Additional points to mention:


The Springvale mine must not be allowed to release up to 32 ML/day of treated mine water into the Coxs River which is part of Sydney's drinking water supply.

The Coxs River is not a drain for mine water. The river must be restored to health, because it flows through our Blue Mountains World Heritage Area.

The release of treated mine water will increase the nutrient status of the Coxs River and possibly lead to massive outbreaks in aquatic weeds or algal blooms downstream

Kaili Leadbeatter
905 Naughtons Gap Rd
Bentley New South Wales 2480
Saturday, October 29, 2016 - 18:22

maria fitzgerald
Object
katoomba , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Maria Fitzgerald
53 Darley st
Katoomba New South Wales 2780
Saturday, October 29, 2016 - 14:27

james bertherton
Object
bondi beach , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

James Bretherton
4/1 Lucius
Bondi Beach New South Wales 2026
Saturday, October 29, 2016 - 14:20

clare shrimpton
Object
alison , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Clare Shrimpton
707 Alison Rd
ALISON New South Wales 2420
Saturday, October 29, 2016 - 10:01

Meredith Brownhill
Object
katoomba , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Meredith Brownhill
19 Letitia Street
Katoomba New South Wales 2780
Friday, October 28, 2016 - 15:37

Beverley Thompson
Object
wentworth falls , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Beverley Thompson
12 Parkes Street
Wentworth Falls New South Wales 2782
Friday, October 28, 2016 - 14:06

lesley gentles
Object
inala , Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Lesley Gentles
55 Abelia Street.
Inala Queensland 4077
Friday, October 28, 2016 - 09:46

trevor brown
Object
lawson , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Trevor brown
45 Livingstonestone St
Lawson New South Wales 2783
Friday, October 28, 2016 - 06:52

helen zhao
Object
artarmon , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Helen Zhao
2 Broughton Road
Artarmon New South Wales 2064
Thursday, October 27, 2016 - 21:23

joel robinson
Object
katoomba , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

I recently directed and produced a short film towards raising awareness of this extraordinary part of our country.

https://www.youtube.com/watch?v=4XY4kEESC6E

We need to save it, as well as prevent possible contamination of our precious water supply, at all costs. These landscapes and their waterways will become popular tourist destinations. it is already happening - even the Lithgow planers are beginning to promote the transition, after generations of refusal to consider a future separate from mining. I urge you to join with the growing movement for protection and change along the western edge of the Blue Mountains.


The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Joel Robinson
1/272 Katoomba Street
Katoomba New South Wales 2780
Thursday, October 27, 2016 - 17:23

soheyla gholamshahi
Object
edgecliff , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

I have not made a reportable political donation and I agree that the Department may publish this submission. Thank you for the opportunity to make a submission on the Springvale Water Treatment proposal.

Yours sincerely,
Dr. Soheyla Gholamshahi

Soheyla Gholamshahi
17/2 New Mclean Street
Edgecliff New South Wales 2027
Thursday, October 27, 2016 - 15:57

Robin Hanson
Object
mt kuring-gai , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

As a resident of Sydney I object to this proposal on three grounds:
* It would contaminate part of the water supply that all Sydneysiders drink
* It would damage Coxs River; its ecology and tourist amenity
* Further damage to the Newness Plateau, its endangered ecosystems and the
pagodas is possible
The Springvale water treatment proposal is absolutely inadequate to protect the Coxs River Catchment, the Blue Mountains World Heritage Area and Sydney's drinking water supply.

Surely it is possible to store water for future use and to adequately treat it before mine water is discharged. Only water treated to a standard that ensures adequate protection of river ecology and tourist amenity should be discharged into the environment. To save on costs of water treatment and transfer, surely several mines could co-operate with transfer and treatment.
Any runoff from local areas, such as the fly ash emplacement areas should be collected and treated for use.

I am also concerned about the possibility of more pipeline construction on the Newnes Plateau. This is one of my favourite bush walking locations and it is already a mish-mash of management and services. No more damage to the plateau, its endangered ecosystems, the pagodas and the landscape amenity is acceptable Yours Faithfully Robin Hanson


Robin Hanson
22 Alicia Rd
MT KURING-GAI New South Wales 2080
Thursday, October 27, 2016 - 13:23

anthony marsh
Object
Leichardt , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

Not my words but I fully endorse them. The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment propoal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

ANTHONY MARSH
17 North Avenue
Leichhardt New South Wales 2040
Thursday, October 27, 2016 - 10:34

Margaret Hilder
Object
little hartley , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Magaret Hilder
90 Bonnie Blink Drive
Little Hartley New South Wales 2790
Wednesday, October 26, 2016 - 22:46

lachlan smith
Object
killara , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Yours faithfully,

Lachlan Smith

Lachlan Smith
20 Spencer Rd
Killara New South Wales 2071
Wednesday, October 26, 2016 - 21:06

andy horsfall
Object
Wentworth Falls , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

andy horsfall
10 langford st
wentworth falls New South Wales 2782
Wednesday, October 26, 2016 - 16:58

Colin Walters
Object
alexandria , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Colin Walters
7a Power Avenue
Alexandria New South Wales 2015
Wednesday, October 26, 2016 - 16:21

Robert Sterry
Object
kurrajong hills , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Robert Sterry
9 Baileys Lane
Kurrajong Hills New South Wales 2758
Monday, October 24, 2016 - 11:51

Pagination

Project Details

Application Number
SSD-7592
Assessment Type
State Significant Development
Development Type
Water supply & management
Local Government Areas
Lithgow City
Decision
Approved
Determination Date
Decider
IPC-N
Last Modified By
SSD-7592-Mod-11
Last Modified On
28/03/2025

Contact Planner

Name
Anthony Ko