Planning proposals
Beverly Hills Town Centre (West)
Georges River
The NSW Government is seeking community feedback on a rezoning proposal for Beverly Hills Town Centre (West) that could deliver around 800 new homes and approximately 191 local jobs in the heart of Beverly Hills.
The proposal would transform approximately 1.7 hectares of land at 407–511 King Georges Road into a mixed-use precinct with new homes, retail and commercial opportunities, improved public spaces, and better pedestrian connections.
Located within walking distance of Beverly Hills train station, the precinct is well positioned to accommodate additional housing, close to transport, services and employment opportunities, supporting a more connected and accessible community.
The proposal is currently on public exhibition until 5 pm Thursday, 10 September 2026.
About the proposal
Beverly Hills has long been earmarked as an area for renewal, with planning investigations dating back to the 1990s.
The Department of Planning, Housing and Infrastructure has prepared a State Assessed Rezoning Proposal supported by detailed urban design analysis and technical studies.
Key features
The proposal could deliver:
- around 800 new homes, including a 2 per cent affordable housing contribution, or equivalent monetary contribution, phased in over time, close to public transport
- building heights ranging from 15 to 22 storeys
- approximately 191 local jobs through new retail and commercial opportunities
- enhanced public spaces and pedestrian connections, including potential for new through-site links to improve access and activity across the precinct.
Detailed flood modelling and other technical assessments have informed the proposal. These studies found future development can be accommodated through appropriate design measures while addressing key considerations such as flooding, traffic and infrastructure capacity.
Future development would also contribute to local and state infrastructure through established planning contribution frameworks.
Have your say
We want to hear your feedback on the Beverly Hills Town Centre (West) proposal.
You can view the exhibition documents below and make a submission until 5 pm 10 September 2026.
The Department hosted a community drop-in session where all community members including residents, businesses and landowners, could speak with project team members and ask questions about the proposal. The session was held on Wednesday 5 August from 5 pm to 8 pm. Thanks to everyone who registered and attended the session.
Mandarin and Cantonese interpreters were available at the session.
For more information, contact the project team at: [email protected]
Exhibition documents
Exhibition documents
Technical Studies
Technical Studies
- Urban Design Report Beverly Hills Town
- Specialist Engineering Assessment Report-Servicing (Vinculum 2025)
- Flood Impact and Risk Assessment (GRC Hydro 2026)
- Traffic Impact Assessment (Ason Group 2025)
- Pipeline Hazard Analysis+Addendum (Sherpa 2026)
- Preliminary Site Investigation Statement (Douglas Partners 2025)