Part 5 Activities
Determined
Hickson Road South upgrade
Sydney
Design and construction of Hickson Road South, comprising the upgrade of Hickson Road from the northern side of the Napolean Street intersection connecting to the existing road upgrade north of the High Street Steps, along with utility and drainage upgrades running adjacent to Barton Street, and intersection upgrades
Review of Environmental Factors (REF) (1)
The approved project is described in the REF, as modified by any associated decision statement (see supporting documents).
Review of Environmental Factors
Hickson Road REF
Date : Wed, 01/07/2026 - 10:34
Plans (7)
Architectural Plans
Appendix P - Landscape Architectural Specification
Date : Wed, 01/07/2026 - 10:35
Elevations and sections
Appendix C - Civil Design Report
Date : Wed, 01/07/2026 - 10:35
Landscape plan
Appendix O - Landscape Design Report
Date : Wed, 01/07/2026 - 10:35
Landscape plan
Appendix N - Stage 4 Landscape Plans
Date : Wed, 01/07/2026 - 10:35
Landscape plan
Appendix M - Stage 3 Landscape Plans
Date : Wed, 01/07/2026 - 10:35
Site plans
Appendix B - Stage 4 Civil Plans
Date : Wed, 01/07/2026 - 10:35
Site plans
Appendix A - Stage 3 Civil Plans
Date : Wed, 01/07/2026 - 10:35
Supporting Documents (20)
Access report
Appendix D - Access Report
Date : Wed, 01/07/2026 - 10:35
Air Quality
Appendix E - Air Quality Report
Date : Wed, 01/07/2026 - 10:35
Arborists report
Appendix F - Arborist Report
Date : Wed, 01/07/2026 - 10:35
Contamination and/or remediation action plan
Appendix W - Contamination Environmental Management Plan
Date : Wed, 01/07/2026 - 10:35
Flood risk management report
Appendix J - Flood Report
Date : Wed, 01/07/2026 - 10:35
Geotechnical report
Appendix K - Geotechnical Report
Date : Wed, 01/07/2026 - 10:35
Heritage impact statement
Appendix R - Statement of Heritage Impact
Date : Wed, 01/07/2026 - 10:35
Other
Appendix L - Archaeology
Date : Wed, 01/07/2026 - 10:35
Other
Appendix U - Lighting Plans Stage 3 and Stage 4
Date : Wed, 01/07/2026 - 10:35
Other
Appendix X - Schedule 5 Industry and Employment SEPP Assessment FINAL
Date : Wed, 01/07/2026 - 10:35
Other
Appendix V - Utilities Plans
Date : Wed, 01/07/2026 - 10:35
Other
Appendix S - Transport
Date : Wed, 01/07/2026 - 10:35
Other
Appendix T - Signage & Wayfinding
Date : Wed, 01/07/2026 - 10:35
Other
Appendix Q - PSI
Date : Wed, 01/07/2026 - 10:35
Other
Appendix I - CPTED Report
Date : Wed, 01/07/2026 - 10:35
Other
Appendix H - Preliminary CTEMP
Date : Wed, 01/07/2026 - 10:35
Other
Appendix G - Noise & Vibration Assessment
Date : Wed, 01/07/2026 - 10:35
System generated document
Part 5 Activity Form.pdf
Date : Wed, 01/07/2026 - 10:35
System generated document
Registration Summary 1782979403.pdf
Date : Wed, 01/07/2026 - 10:35
Traffic report
Appendix B1 - TCS Plan 4625 - Traffic Signals at Hickson Road, Sussex Street and Napolean Street
Date : Wed, 01/07/2026 - 10:35
Activity Details
Reference number
P5-2026-184
Proponent(s)
Infrastructure Nsw (Department Of Premier And Cabinet)
Address
Hickson Road
Barangaroo Nsw 2000
Barangaroo Nsw 2000
Legislation
TISEPP (State Environmental Planning Policy (Transport & Infrastructure) 2021)
Activity Type
Roads and road infrastructure facilities
Decision
Approved
Determination date