CIV > $5M - Council interest
Determined
231-233 Argyle Street, Moss Vale
Southern Regional Planning Panel
Construction of a shopping centre including Woolworths and speciality retail, commercial and car wash , associated works including traffic light intersection works
(including traffic signals).
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
Determination Statement of Reasons - PPSSTH-314 (SECURED)
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
PPSSTH-314 - Planning Panels Declarations - combined (SECURED)
Late information received (12)
Late information received
Item 12. Letter to Woolworths Group Limited (Moss Vale) on subdivision planning principle
Late information received
Item 11. Bowral South NLA Retail Needs Assessment v2 commissioned by Council
Late information received
Item 10. Updated Acoustic Asessment lodged with Council 19 April 2024
Late information received
Item 9. TfNSW Concurrence
Late information received
Item 8. Mills Oakley Letter of Advice submitted to Council 20 November 2025
Late information received
Item 7. Location IQ Economic Presentation to Panel 20052025
Late information received
Item 6. Development Control Enquiry - Pre Lodgement Meetin
Late information received
Item 5. Council E zones submission to DPE_AI-1410660
Late information received
Item 4. Correspondence with TfNSW on truck movements
Late information received
Item 3. Correspondence with Council on existing truck movements
Late information received
Item 1. Woolworths Presentation to Southern Region Planning Panel Moss Vale Public Determination Meeting
Late information received
CBRK Response to traffic reasons for refusal 20.05.25
Council Assessment Report (1)
Council Assessment Report
Panel Report - 231 -233 Argyle Street Moss Vale
Attachments to Council Assessment Report (11)
Attachment to assessment report
Attachment 4 - Amended Architecetural Plans
Attachment to assessment report
Attachment 5 - Amended Landscape Plan
Attachment to assessment report
Attachment 7 - EIA - Applicant
Attachment to assessment report
Attachment 8 EIA Response - Applicant - Oct 24
Attachment to assessment report
Attachment 10 - SEE
Attachment to assessment report
Attachment 6 - TfNSW Concurrence
Attachment to assessment report
Attachment 9 - Peer Review of EIA May 24 & Feb 25
Attachment to assessment report
Attachment 2 - DCP Assessment
Attachment to assessment report
Attachment 1 - Internal & External Responses Table
Attachment to assessment report
Attachment 11 - DA Form
Attachment to assessment report
Attachment 3 - Recommended Reasons for Refusal
Record of Briefing (2)
Record of Site Visit (2)
Other (1)
Notice of Panel Meeting
PPSSTH-314 - Notice of Public Meeting 20.05.2025 (register to receive details)
Links (1)
URL
Southern Regional Planning Panel - Audio recording – PPSSTH-314 – 20 May 2025
Meetings
Public determination meeting
Chaired by:
Chris Wilson
Project Details
DA
number
24/0212
Planning panel reference number
PPSSTH-314
Capital investment value
$29,821,861
Project Address
233 Argyle Street Moss Vale 2577
Lodgement date
Referral date
Local government
Wingecarribee Shire Council
Type of matter
DA
Determination outcome
Refused
Determination Date