Capital Investment Value > $30M

Determined

Mixed Use Development Application

Sydney Eastern City Planning Panel

Demolition of existing buildings, removal of six (6) trees and the construction of a part 11, part 13 storey mixed-use development comprising 172 dwellings, three (3) ground floor commercial spaces and four (4) basement levels comprising 235 car parking spaces, and ancillary and landscaping works.

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
PPSSEC-112 - Determination SOR

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
PPSSEC-112 - Panel declaration forms

Council Assessment Report (1)

Council Assessment Report
DA2020.256 Final Assessment Report and Conditions

Attachments to Council Assessment Report (27)

Attachment to assessment report
LOC - TAHE
Attachment to assessment report
GTA - Water NSW
Attachment to assessment report
GTA - TfNSW
Attachment to assessment report
GTA - Sydney Trains
Attachment – amended plans
DA202.256 Response to RFI Covering Letter - 2-6 Pilgrim Ave & 11
Attachment – amended plans
DA202.256 Final Documents - Attachment S - Electrolysis and Stra
Attachment – amended plans
DA202.256 Final Documents - Attachment R - Derailment Risk Asses
Attachment – amended plans
DA202.256 Final Documents - Attachment Q - Structural Report
Attachment – amended plans
DA202.256 Final Documents - Attachment P - Stormwater Covering L
Attachment – amended plans
DA202.256 Final Documents - Attachment P - Revised Stormwater Pl
Attachment – amended plans
DA202.256 Final Documents - Attachment O - BASIX Certificate
Attachment – amended plans
DA202.256 Final Documents - Attachment N - Revised Section J Rep
Attachment – amended plans
DA202.256 Final Documents - Attachment M - Revised Energy Effici
Attachment – amended plans
DA202.256 Final Documents - Attachment L - Additional Site Inves
Attachment – amended plans
DA202.256 Final Documents - Attachment K - Revised Waste Managem
Attachment – amended plans
DA202.256 Final Documents - Attachment J - Traffic and Parking R
Attachment – amended plans
DA202.256 Final Documents - Attachment I - Revised Noise Impact
Attachment – amended plans
DA202.256 Final Documents - Attachment I - Final Noise and Vibra
Attachment – amended plans
DA202.256 Final Documents - Attachment H - Natural Ventilation R
Attachment – amended plans
DA202.256 Final Documents - Attachment G - Clause 4.6 Variation
Attachment – amended plans
DA202.256 Final Documents - Attachment F - Amended ADG Complianc
Attachment – amended plans
DA202.256 Final Documents - Attachment E - Design Verification S
Attachment – amended plans
DA202.256 Final Documents - Attachment E - Amended SEPP 65 Repor
Attachment – amended plans
DA202.256 Final Documents - Attachment D - Amended Landscape Pla
Attachment – amended plans
DA202.256 Final Documents - Attachment B - Detailed Response To
Attachment – amended plans
DA202.256 Final Documents - Attachment A - Detailed Response to
Attachment – amended plans
Final Documents - Attachment C - Amended Architectural Drawings

Record of Briefing (2)

Record of Briefing
PPSSEC-112 Record of Briefing 10 June 21
Record of Briefing
PPSSEC-112 - Record of Briefing 22 April 2021

Other (2)

Notice of Panel Meeting
PPSSEC-112 - videoconference - Advert-23 Sept
URL
Sydney Eastern City Planning Panel meeting - 23 September 2021 - PPSSEC-112 Strathfield - DA2020/256

Links (1)

URL
Sydney Eastern City Planning Panel meeting - 23 September 2021 - PPSSEC-112 Strathfield - DA2020/256

Project Details

DA number
DA2020/256
Planning panel reference number
PPSSEC-112
Capital investment value
$46,179,507
Project Address
2 Pilgrim Avenue Strathfield 2135,6 Pilgrim Avenue Strathfield 2135,11 Albert Road Strathfield 2135,13 Albert Road Strathfield 2135
Lodgement date
Referral date
Local government
Strathfield Municipal Council
Type of matter
DA
Determination outcome
Approved