Designated Development - Waste Facility
Determined
Proposed FOGO Composting Facility
Southern Regional Planning Panel
Proposed waste management facility for the purpose of sorting and composting a maximum of 10,00 tonnes per annum of organic material, including food organics garden organics (FOGO), and associated access and supporting infrastructure.
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
PPSSTH-83 - FINAL - Determination & SOR - signed
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
PPSSTH-83 - Planning Panels Meeting Declarations - combined
Supplementary Council Assessment Report (1)
Supplementary Council Assessment Report
Supplementary Report - PPSSTH-83 - Snowy - FOGO, Gilmore
Council Assessment Report (1)
Council Assessment Report
Council Planning Report - FOGO - Gilmore
Attachments to Council Assessment Report (8)
Attachment to assessment report
Attachment 7 - EPA GTAs
Attachment to assessment report
Attachment 2 - Development Plans
Attachment to assessment report
Attachment 3 - Environmental Impact Statement
Attachment to assessment report
Attachment 1 - SEARs
Attachment to assessment report
Attachment 8 - Heritage NSW GTAs
Attachment to assessment report
Attachment 5 - DCP Assessment
Attachment to assessment report
Attachment 6 - Recommended Conditions of Consent
Attachment to assessment report
Attachment 4 - External Responses Table
Record of Briefing (1)
Record of Briefing
Record of Briefing PPSSTH-83 - 2 August 2022
Record of Site Visit (1)
Record of Site Visit
Record of Site Inspection 06 April 2022
Other (6)
Attachment to supplementary assessment report
Attachment 5 - Amended Recommended Conditions of Consent - 15 November 22
Attachment to supplementary assessment report
Attachment 3 - Aboriginal Cultural Heritage Assessment
Attachment to supplementary assessment report
Attachment 1 - EPA GTAs
Attachment to supplementary assessment report
Attachment 6 - Biodiversity Assessment
Attachment to supplementary assessment report
Attachment 4 - Heritage NSW GTAs
Attachment to supplementary assessment report
Attachment 2 - DPIE (BCD) Correspondence
Project Details
DA
number
DA2021/0011
Planning panel reference number
PPSSTH-83
Capital investment value
$1,545,455
Project Address
Snowy Mountains Highway Gilmore 2720
Lodgement date
Referral date
Local government
Snowy Valleys Council
Type of matter
DA
Determination outcome
Approved