Designated Development - Extractive Industry
Determined
Quarry
Western Regional Planning Panel
The application is for the development and operation of an open-cut Quarry (the Proposal).
The Proposal would comprise: extraction of up to 960,000m3 or approximately 2.3 million tonnes (Mt) of material at an average rate of 80,000 tonnes per annum (tpa) and a maximum rate of 150,0000tpa for a period of approximately 30 years; crushing, screening and stockpiling of the extracted material as required; transportation of the extracted material from the Project Site; and construction of site infrastructure.
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
Determination Statement of Reasons PPSWES-262
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
Completed panel declaration forms
Other (8)
Other
PPSWES-262 Applicant response to draft conditions and GTAs
Other
Appendix D ADDITIONAL INFORMATION_P-1339260
Other
Appendix C EIS_P-1339260
Other
Appendix B DRAFT CONDITIONS_M-428090
Other
Appendix A EPA GTAs_M-428090
Other
Appendix E AGENCIES_M-428090
Other
Appendix F SUBMISSION (1)_M-428090
Other
DA 2024-166 COUNCIL ASSESSMENT REPORT_M-428090
Project Details
DA
number
DA 2024/0166
Planning panel reference number
PPSWES-262
Capital investment value
$579,842
Project Address
Canowindra Road Canowindra 2804
Lodgement date
Referral date
Local government
Cabonne Shire Council
Type of matter
DA
Determination outcome
Approved
Determination Date