CIV > $5M - Council interest
Determined
Redleaf
Western Regional Planning Panel
Residential subdivision (164 lots) site preparation, demolition works, bulk earthworks, dam dewatering, tree removal (26 trees), stormwater management system and sewer pump station.
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
Decision and Statement of Reasons PPSWES-309
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
Planning Panel member Declaration of Interest PPSWES-309
Council Assessment Report (1)
Council Assessment Report
WRPP - 14 April 2026 - DA 2982025(1) - Planning Assessment Report to WRPP - 3 Redmond Place, 154 Lone Pine Avenue and 5255 Mitch
Attachments to Council Assessment Report (15)
Attachment to assessment report
WRPP - 14 April 2026 - DA 2982025(1) - Appendix Z - Letter of Offer - Planning Agreement - 3 Redmond Place
Attachment to assessment report
WRPP - 14 April 2026 - DA 2982025(1) - Appendix B - Orange DCP Assessment - 3 Redmond Place
Attachment to assessment report
WRPP - 14 April 2026 - DA 2982025(1) - Appendix A - Redmond Place DCP Table - 3 Redmond Place
Attachment to assessment report
WRPP - 14 April 2026 - DA 2982025(1) - Other - Proponent Response to RFI - 3 Redmond Place
Attachment to assessment report
WRPP - 14 April 2026 - DA 2982025(1) - External Agencies - TfNSW Response - 3 Redmond Place, Orange
Attachment to assessment report
WRPP - 14 April 2026 - DA 2982025(1) - External Agencies - NSW RFS - S100B ~f Approval - 3 Redmond Place - 154 Lone Pine Avenue
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix AC - Signage Plans - 3 Redmond Place
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix Q - Subdivision Plan - Stage 3 Plans [3 Redmond Place]
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Other - Lighting Plan - 3 Redmond Place
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix E - Civil Engineering Plan - 3 Redmond Place
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Other - Draft Deposited Plan - Stage 3 [3 Redmond Place]
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix R - Subdivision Plan - Stage 4 Plans [3 Redmond Place]
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix O - Subdivision Plan - Stage 1 Plans [3 Redmond Place]
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix P - Subdivision Plan - Stage 2 plans [3 Redmond Place]
Attachment – plans
WRPP - 14 April 2026 - DA 2982025(1) - Appendix G - Landscape plan - 3 Redmond Place
Other (35)
Other
WRPP - 14 April 2026 - DA 298 2025(1) - DRAFT Conditions - 3 Redmond Place, 154 Lone Pine Avenue and 5255 Mitchell Highway - v3
Other
WRPP - 14 April 2026 - DA 298 2025(1) - DRAFT Conditions - 3 Redmond Place, 154 Lone Pine Avenue and 5255 Mitchell Highway
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix D - Cost Estimate Report - 3 Redmond Place - NOT FOR PUBLIC EXHIBITION
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix Y - Traffic Impact Assessment - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix N - Archaeological Assessment - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix D - Cost Estimate Report - 3 Redmond Place - FOR PUBLIC EXHIBITION
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix W - Crime Prevention through Environmental Design (CEPTED) - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Flood Risk Management Report - 3 Redmond Place - [Appendix T - Flood Maps] - REFER ADDEND
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix L - Geotechnical Report - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix AA - Redmond Place Open Space Consultation Feedback Report
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix X - Road Safety Audit [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix V - Infrastructure Servicing Assessment [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix J - Detailed Site Investigation - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix F - Site Survey Plan - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix M - Southern Feeder Road Stage 3 Traffic Noise Assessment - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix T - Water Cycle Management Plan - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix U - Bushfire Assessment Report - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix I - Biodiversity Assessment Report - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix H - Arborists report - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - Draft Section 88B - Stage 1 [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - Draft Section 88B - Stage 3 [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - Draft Section 88B - Stage 2 [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - Draft Section 88B - Stage 4 [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - 3 Redmond Place - [Billboard Lighting Cover Letter]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - 3 Redmond Place - [Billboard Lighting Product Sheet - Telescopic Led Floodlight]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Other - 3 Redmond Place - [Billboard Lighting Light-Dispersion Chart]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix AB - Sewer and Water Plans - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix K - Remedial Action Plan [3 Redmond Place]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Statement of environmental effects - 3 Redmond Place - [Amended SEE]
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix T Addendum - Water Cycle Management Plan (ADDENDUM) - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix T Addendum - Water Cycle Management Plan (ADDENDUM cover letter) - 3 Redmond Pla
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix E - Civil Engineering Plan - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix T Addendum - Water Cycle Management Plan (ADDENDUM) - 3 Redmond Place
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix T Addendum - Water Cycle Management Plan (ADDENDUM cover letter) - 3 Redmond Pla
Other
WRPP - 14 April 2026 - DA 2982025(1) - Appendix E - Civil Engineering Plan - 3 Redmond Place
Project Details
DA
number
DA 298/2025(1)
Planning panel reference number
PPSWES-309
Capital investment value
$56,561,020
Project Address
3 Redmond Place Orange 2800,154 Lone Pine Avenue Orange 2800,5255 Mitchell Highway Orange 2800
Lodgement date
Referral date
Local government
Orange City Council
Type of matter
DA
Determination outcome
Approved
Determination Date