Skip to main content

Capital Investment Value > $30M

Determined

Seniors housing development

Sydney North Planning Panel

Demolition of existing structures and construction of a seniors housing development comprising 94 bed residential care facility, 162 independent living units and ancillary works

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
PPSSNH-22 Determination SOR 9 Dec 2020

Completed Panel Declaration forms (2)

Completed Panel Declaration forms
PPSSNH-22 Panel Declarations 9 Dec 2020
Completed Panel Declaration forms
PPSSNH-22 Panel Declarations 11 Dec 2019

Record of Deferral (1)

Record of deferral
PPSSNH-22 Record of Deferral 11 Dec 2019

Council Assessment Report (8)

Council Assessment Report
Attachment 7 Campus Plan and Registered Dealings
Council Assessment Report
Attachment 3 Architectural Plans
Council Assessment Report
Attachment 5 Civil Plans
Council Assessment Report
Attachment 4 Landscape Plans
Council Assessment Report
Attachment 6 Clause 4.6 Variation Request
Council Assessment Report
Attachment 2 Development Site Lot Area Plan
Council Assessment Report
Attachment 1 Locality Plan
Council Assessment Report
Assessment Report

Record of Briefing (1)

Record of Briefing
PPSSNH-22 Record of Briefing 11 Sept 2019

Other (12)

Attachment to supplementary assessment report
Attachment 9 Perspective Views
Attachment to supplementary assessment report
Attachment 8 Clause 4.6 Submission
Attachment to supplementary assessment report
Attachment 7 Civil Plan Extracts
Attachment to supplementary assessment report
Attachment 6 Landscape Plan and Sections
Attachment to supplementary assessment report
Attachment 5 Elevation Extracts
Attachment to supplementary assessment report
Attachment 4 Floor Plans
Attachment to supplementary assessment report
Attachment 3 Staging Plan
Attachment to supplementary assessment report
Attachment 2 Site Plans
Attachment to supplementary assessment report
Attachment 1 Locality Plan
Notice of Panel Meeting
Notice of Meeting 11 Dec 2019 Hornsby
Supplementary assessment report
Supplementary Assessment Report
URL
Audio recording of public meeting 11 Dec 2019

Links (1)

URL
Audio recording of public meeting 11 Dec 2019

Meetings

Public determination meeting

Chaired by: Mr Peter Debnam

Electronic determination

Chaired by: Mr Peter Debnam

Project Details

DA number
DA/315/2019
Planning panel reference number
PPSSNH-22
Capital investment value
$230,973,000
Project Address
284 Castle Hill Road Castle Hill 2154
Lodgement date
Referral date
Local government
The Council Of The Shire Of Hornsby
Type of matter
DA
Legal appeal description
Class 1 Legal Appeal
Determination outcome
Refused