Capital Investment Value > $30M

Determined

Shop Top Housing

Hunter & Central Coast Regional Planning Panel

Construction of Shop Top Housing & Demolition of Existing Structures (Nominated Integrated)(RPP)

Determination and Statement of Reasons (2)

Determination and Statement of Reasons
Court Judgment 02 April 2026
Determination and Statement of Reasons
Court Judgment (Annexure A)

Record of Briefing (1)

Record of Briefing
PPSHCC-322 - Record of Briefing

Project Details

DA number
DA/1283/2024
Planning panel reference number
PPSHCC-322
Capital investment value
$35,429,412
Project Address
43 The Esplanade Ettalong Beach 2257,44 The Esplanade Ettalong Beach 2257,45 The Esplanade Ettalong Beach 2257,46 The Esplanade Ettalong Beach 2257
Lodgement date
Referral date
Local government
Central Coast Council
Type of matter
DA
Legal appeal description
Appeal upheld and DA approved by Land and Environment Court on 02 April 2026
Determination outcome
Approved
Determination Date
Court decision
Approved
Date of court decision