Skip to main content

CIV > $5M - Private infrastructure and community facilities

Determined

Solar Electricity Generation Facility

Northern Regional Planning Panel

Establishment of a 5MW Solar PV Electricity Generation Facility with Associated Infrastructure

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
Determination PPSNTH-66

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
Completed declaration forms PPSNTH-66

Council Assessment Report (1)

Council Assessment Report
Liverpool Plains - Council Assessment Report - DA 48-2020

Attachments to Council Assessment Report (6)

Attachment to assessment report
Annexure E - DA 48-2020 - Response to Submissions
Attachment to assessment report
Annexure C - DA 48-2020 - Responses from External Agencies
Attachment to assessment report
Annexure A - DA 48-2020 - Technical Reports
Attachment to assessment report
Annexure A - DA 48-2020 - Statement of Environmental Effects
Attachment to assessment report
Annexure A - DA 48-2020 - Architectural Survey Landscape Plans
Attachment – recommended conditions of consent
Annexure B - DA 48-2020 - Recommended Conditions of Consent - 22

Links (1)

URL
Audio recording – PPSNTH-66 – 29 April 2021

Meetings

Public determination meeting

Chaired by: Mr Paul Mitchell

Project Details

DA number
DA 48/2020
Planning panel reference number
PPSNTH-66
Capital investment value
$6,903,503
Project Address
962 Black Gully Road Werris Creek 2341
Lodgement date
Referral date
Local government
Liverpool Plains Shire Council
Type of matter
DA
Determination outcome
Approved