DA Exhibitions
Determined
DA 13-11-2018 Alterations and additions to existing building for use as a data centre at 5 Parkview Drive
Sydney Olympic Park
Alterations and additions to existing warehouse building, including installation of generators and cooling plant, for use as a data centre
Attachment and Resources
Attachment and Resources
- 1_Statement of Environmental Effects_ 5 Parkview Drive.pdf
- 190116- Data Centre_ Request For Further Information.pdf
- DA 13-11-2018 - 0_DA Form & Landowners Consent.pdf
- DA 13-11-2018 - 6_Hazard Risk Assessment.pdf
- DA 13-11-2018 - 11_Waste Management Plan.pdf
- DA 13-11-2018 3_Arborist Report.pdf
- DA 13-11-2018 4_Quantity Surveyors Report.pdf
- DA 13-11-2018 5_Acoustic Assessment Report.pdf
- DA 13-11-2018 7_ Flood Risk Assessment.pdf
- DA 13-11-2018 8_ Geotechnical Preliminary Investigation
- DA 13-11-2018 9_BCA Capability Statement.pdf
- DA 13-11-2018 10_Landscape Design.pdf
- DA 13-11-2018 12_Site Survey & Architectural Package.pdf
- DA 13-11-2018 Acoustic Assessment Report.pdf
- DA 13-11-2018 dev consent.pdf
- DA 13-11-2018 Response to Sydney Olympic Park Letter.pdf
- SGIA Meeting Request 29.01.2019 v2-2.pdf
Project Details
Portal reference number
DA 13-11-2018
Consent authority's ID number
DA 13-11-2018
Property Address
5 Parkview Drive
Type of application
Development Application
Type of development
Alterations and additions
Determining authority
Decision
Approved
Consent Authority
Consent authority name
Minister for Planning and Public Spaces