Collector Wind Farm

Upper Lachlan Shire

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Assessment
  6. Recommendation
  7. Determination

60-80 turbine wind farm, with the capacity to generate up to 160 MW of electricity, plus ancillary infrastructure (including underground cabling, substation, grid connection, and access tracks).

Consolidated Consent

Consolidated Project Approval

Archive

Application (7)

DGRs (3)

EA (31)

Response to Submissions (3)

Recommendation (5)

Determination (3)

Approved Documents

Management Plans and Strategies (11)

Reports (5)

Independent Reviews and Audits (2)

Notifications (3)

Other Documents (6)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

Penalty Notice issued to Collector Wind Farm Pty Ltd (MP 10_0156, Upper Lachlan Council LGA)

On 13 March 2020, the Department issued a $6000 Penalty Notice to Collector Wind Farm (CWF), for failing to obtain Construction Certificates under the Environmental Planning and Assessment Act 1979 for the construction of turbine foundations at the Collector Wind Farm.  CWF have since lodged an application for obtaining a building certificate for the foundations with the local Council. 

Inspections

23/05/2024

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Project Details

Application Number
MP10_0156
Assessment Type
State Significant Development
Local Government Areas
Upper Lachlan Shire
Decision
Approved With Conditions
Determination Date
Decider
IPC-N
Last Modified By
MP10_0156-Mod-3
Last Modified On
16/08/2019

Contact Planner

Name
Iwan Davies