State Significant Development

Determination

Great Western Battery Energy Storage System

Lithgow City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Development of a 500 MW battery energy storage facility with associated infrastructure

Attachments & Resources

Notice of Exhibition (1)

EIS (15)

Response to Submissions (7)

Agency Advice (12)

Additional Information (9)

Determination (3)

Approved Documents

There are no post approval documents available

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

There are no inspections for this project.

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 3 of 3 submissions
Name Withheld
Object
MONT ALBERT , Victoria
Message
There is insufficient justification for this project to be established on rural land. There are appropriate alternative locations on existing industrial land in the local vicinity. Please justify why industrial land was not utilised.
Colin BARKER
Object
PORT MACQUARIE , New South Wales
Message
1. The BESS (Battery Energy Storage System) should be built on industrial land not on rural land as proposed.
As attached is Wallerawang Zoning map showing Industrial land close to Transgrid substation in our opinion is a better option.
2. This project is not what we were told orginally and found the information in the community information booklet to be misleading
3. Nothing was ever mentioned about noise walls per Fig 18-12, fig 18-14. Attached is pictures of our daily views from driveway and backyard.
4. We are concerned about the walls that will be erected for potential explosions and fires as no other sites have walls surrounding them.
5. We should not have to put up with vegetation around our house to stop noise and our view.
.
Lithgow City Council
Comment
Lithgow , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
SSD-12346552
Assessment Type
State Significant Development
Development Type
Electricity Generation - Other
Local Government Areas
Lithgow City
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Kurtis Wathen