State Significant Development
Mayfield West Waste Facility
Newcastle City
Current Status: Determination
Interact with the stages for their names
- SEARs
- Prepare EIS
- Exhibition
- Collate Submissions
- Response to Submissions
- Assessment
- Recommendation
- Determination
Consolidated Consent
Modifications
Archive
Request for DGRS (1)
DGRs (1)
EIS (4)
Response to Submissions (12)
Amendments (2)
Recommendation (2)
Determination (3)
Approved Documents
Management Plans and Strategies (5)
Reports (10)
Independent Reviews and Audits (3)
Notifications (2)
Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.
Complaints
Want to lodge a compliance complaint about this project?
Make a ComplaintEnforcements
There are no enforcements for this project.
Inspections
There are no inspections for this project.
Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.
Submissions
peter auckett
Object
peter auckett
Message
Name Withheld
Object
Name Withheld
Message
I live in the neighbourhood in which the Mayfield West Recycling Plant wishes to increase its load. In this neighbourhood already - we are exposed to One Steels noise and pollution, the rail line noise and pollution, Incitec's noise and pollution. At this point in time - I can only see more noise, more pollution, more dust and more traffic involved with the further up sizing of the Recycling Plant. How about we give the local residents a break or maybe with the up sizing of the plant - reimburse the local residents insulation because I have no doubt the local dust will increase as with the workload of the recycling plant. My house is already filled with dust - I seriously don't want any more. How about we let Mayfield regenerate itself after so many years of being abused.
Hunter Water Corporation
Comment
Hunter Water Corporation
Message
1. Development Application.
2. Hydraulic Assessment Application.
3. Trade Wastewater Application.
Connection to the Hunter Water network will not be permitted without the completion of these applications and all requirements satisfied by the applicant.