State Significant Development

Determination

Raymond Avenue Multi-level Warehouse Matraville

Randwick City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Construction and operation of a two level warehouse and distribution centre at 42 Raymond Avenue, Matraville

Consolidated Consent

MOD-1 Consolidated Conditions

Archive

Notice of Exhibition (1)

Early Consultation (2)

SEARs (2)

EIS (35)

Response to Submissions (26)

Agency Advice (12)

Additional Information (2)

Recommendation (2)

Determination (5)

Approved Documents

Management Plans and Strategies (22)

Reports (2)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

30/05/2023

17/01/2024

23/01/2024

9/02/2024

12/02/2024

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 9 of 9 submissions
Matraville Precinct
Comment
MATRAVILLE , New South Wales
Message
Please see attached file
Attachments
Ian Levitt
Object
Matraville , New South Wales
Message
Matraville is becoming more residential.
New Town houses Residential homes have been built meters away from this site
All heavy vehicle traffic need to be kept away from Macaulie St between Austalia Ave and Perry St
Raymond Ave needs to be closed at Harold st intersection to prevent heavy vehicles using this resedential end.
Aproval of such development should not be state signicant and should be up to the local concil and its residents
Name Withheld
Object
ULTIMO , New South Wales
Message
There is already not enough street parking in the area to support the growth of industrial warehouse and office area.
Too many trucks are already entering McCauley St and Raymond Avenue and causing noise and disturbance to the neighbourhood.
Name Withheld
Object
MATRAVILLE , New South Wales
Message
The application does not clearly state the warehouse use or operation hours. Is this a 24/7 operation involving more trucks and noise at night. I also disagree with the statement with reference to impact on the community. It says that we are used to living with industrial sites. When I moved to the area over 25 years ago, there was minimal industry. We do not want more industry in the area, the noise generated from the wharfs, paper mill, Orica is overpowering as it is. So your statement saying the residents “will adjust easily” NO WE WONT.

I object to this application based on the grounds that you are letting too much industry into this residential pocket. Enough is enough.

Also I love the fact that you ask to accept the terms and conditions with the NSW a planning and click the link. Guess what. The link is no longer available.
Randwick City Council
Comment
Randwick , New South Wales
Message
Attachments
Bayside City Council
Comment
Rockdale , New South Wales
Message
Attachments
Bayside City Council
Comment
Rockdale , New South Wales
Message
Attachments
Randwick City Council
Comment
Bayside Council
Comment
ROCKDALE , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
SSD-31552370
Assessment Type
State Significant Development
Development Type
Warehouse or distribution centres
Local Government Areas
Randwick City
Decision
Approved
Determination Date
Decider
Director
Last Modified By
SSD-31552370-Mod-2
Last Modified On
06/10/2023

Contact Planner

Name
Catriona shirley