State Significant Development
Determination
Springvale Water Treatment Facility
Lithgow City
Current Status: Determination
Interact with the stages for their names
- SEARs
- Prepare EIS
- Exhibition
- Collate Submissions
- Response to Submissions
- Assessment
- Recommendation
- Determination
Consolidated Consent
Consolidated Consent
Modifications
Determination
Determination
Determination
Determination
Determination
Determination
Withdrawn
Determination
Archive
Request for SEARs (1)
SEARS (1)
EIS (20)
Response to Submissions (2)
Amendments (2)
Recommendation (8)
Determination (3)
Approved Documents
Management Plans and Strategies (13)
Reports (4)
Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.
Complaints
Want to lodge a compliance complaint about this project?
Make a ComplaintEnforcements
There are no enforcements for this project.
Inspections
21/10/2020
10/05/2022
Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.
Submissions
Showing 121 - 140 of 454 submissions
Mark King
Object
Mark King
Object
Moranbah
,
Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Mark King
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Mark King
Beryl Caslick
Object
Beryl Caslick
Object
Chuwar
,
Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Beryl Caslick
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Beryl Caslick
Christopher Bailey
Object
Christopher Bailey
Object
Glebe
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Christopher Bailey
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Christopher Bailey
Suzanne McLellan
Object
Suzanne McLellan
Object
Burnett Heads
,
Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Suzanne McLellan
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Suzanne McLellan
David & Jane Mcbride
Object
David & Jane Mcbride
Object
Surf Beach
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
David and jane Mcbride
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
David and jane Mcbride
Lynette Singleton
Object
Lynette Singleton
Object
Innisfail
,
Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Lynette Singleton
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Lynette Singleton
Annet van Kesteren
Object
Annet van Kesteren
Object
Kings Park
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Annet van Kesteren
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Annet van Kesteren
Janette Angelo
Object
Janette Angelo
Object
Yamba
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Janette Angelo
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Janette Angelo
Anna Stone
Object
Anna Stone
Object
Casino
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Anna Stone
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Anna Stone
Mark Coleman
Object
Mark Coleman
Object
Bato Bay
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Mark Coleman
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Mark Coleman
Janine Perry Brown
Object
Janine Perry Brown
Object
Craisbrook
,
Victoria
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Janine Perry
Brown
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Janine Perry
Brown
Mitzi Saunders
Object
Mitzi Saunders
Object
Killara
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Mitzi Saunders
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Mitzi Saunders
Danny Redford
Object
Danny Redford
Object
Whyala Stuart
,
South Australia
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Danny Redford
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Danny Redford
Kerry McCarthy
Object
Kerry McCarthy
Object
Tiwi
,
Northern Territory
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Kerry McCarthy
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Kerry McCarthy
Janelle J Hosking
Object
Janelle J Hosking
Object
Ormeau
,
Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Janellej Hosking
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Janellej Hosking
Jennifer Pearson
Object
Jennifer Pearson
Object
Gosnells
,
Western Australia
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Jennifer Pearson
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Jennifer Pearson
Paul Baker
Object
Paul Baker
Object
Green Point
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Paul Baker
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Paul Baker
Helen Thomas
Object
Helen Thomas
Object
Armidale
,
New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Helen Thomas
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
Helen Thomas
Lisa Thornton
Object
Lisa Thornton
Object
Pacific Haven
,
Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
I the under signed make this Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
lisa tthornton
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
I the under signed make this Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
lisa tthornton
William Spencer
Object
William Spencer
Object
Morphett Vale
,
South Australia
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
William Spencer
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001
Dear Sir/Madam,
Submission on the Springvale Water Treatment proposal (SSD 16_7592)
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.
Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.
The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.
The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.
To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.
Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.
Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.
William Spencer
Pagination
Project Details
Application Number
SSD-7592
Assessment Type
State Significant Development
Development Type
Water supply & management
Local Government Areas
Lithgow City
Decision
Approved
Determination Date
Decider
IPC-N
Last Modified By
SSD-7592-Mod-11
Last Modified On
28/03/2025
Contact Planner
Name
Anthony
Ko
Related Projects
SSD-7592-MOD-1
Determination
SSD Modifications
Mod 1
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-MOD-2
Determination
SSD Modifications
Mod 2
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-3
Determination
SSD Modifications
Springvale Water Treatment Project MOD 3
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-4
Determination
SSD Modifications
Springvale Water Treatment Project MOD 4
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-5
Determination
SSD Modifications
MOD 5 - extend interim water management strategy time frame
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-6
Determination
SSD Modifications
Springvale WTF MOD 6 - receipt of water from Angus Place
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-7
Determination
SSD Modifications
MOD 7 - extend timeframe water management strategy
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-8
Determination
SSD Modifications
MOD 8 - extend interim water management strategy time frame
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-9
Withdrawn
SSD Modifications
MOD 9 - Extend interim water management strategy timeframe
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-10
Withdrawn
SSD Modifications
MOD 10 - Residuals transfer increase
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790
SSD-7592-Mod-11
Determination
SSD Modifications
MOD 11 - water management during MPPS outages
Water Transfer And Treatment System Between Springvale Mine And Mount Piper Power Station Lithgow, Western Coalfields New South Wales Australia 2790