Complaints
Want to lodge a compliance complaint about this project?
Make a Complaint
Enforcements
Penalty Notice issued to Lipman Pty Ltd (SSD-7942) City of Parramatta LGA
On 16 July 2024, NSW Planning issued a $15,000 Penalty Notice to Lipman Pty Ltd (Lipman) for carrying out construction at the Open Water Surf Facility at Sydney Olympic Park outside of the approved construction hours of 7am-5pm Mondays to Saturdays. On Thursday 28 March 2024, Lipman commenced a concrete pour at approximately 5:40 pm outside the approved construction hours. The construction of the Open Water Surf Facility is now complete.
Penalty Notice issued to Lipman Pty Ltd (SSD-7942) City of Parramatta LGA
On 16 July 2024, NSW Planning issued a $15,000 Penalty Notice to Lipman Pty Ltd (Lipman), for obstruction of the public way with heavy vehicles (Holker Busway, loop road, bicycle path and pedestrian pathway) at the Open Water Surf Facility on 11 March 2024 in breach of the consent. The obstruction of the public way resulted in a complaint to NSW Planning and movement of cyclists from the bicycle path onto the road. The construction of the Open Water Surf Facility is now complete.
Inspections
28/02/2024
5/12/2024
11/12/2024
11/12/2024
Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.