  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Tinda Creek Quarry

Archive

Application (2)

Request for DGRS (1)

DGRs (2)

EIS (19)

Agency Submissions (8)

Response to Submissions (2)

Recommendation (2)

Determination (2)

Approved Documents

Management Plans and Strategies (2)

Agreements (12)

Other Documents (1)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

Official Caution issued to Aus-10 Rhyolite Pty Ltd (SSD-4978) Hawkesbury City LGA 

On 21 December 2022, NSW Planning issued an Official Caution to Aus-10 Rhyolite Pty Ltd for failing to implement the approved Water Management Plan at the Tinda Creek Quarry on 11 October 2022, resulting in water discharging from the Tinda Creek Quarry closed water system.

Inspections

13/04/2022

15/11/2022

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 2 of 2 submissions
Colong Foundation for Wilderness Ltd
Object
Sydney , New South Wales
Message
Mr Carl Dumpleton
Mining and Industry Projects
NSW Department of Planning & Infrastructure
GPO Box 39
Sydney NSW 2001

Dear Mr Dumpleton,

Submission as an objection to Tinda Creek Quarry Project - SSD-4978

Submission as an objection attached.

Thank you for the opportunity to make a submission.

Yours sincerely,

Keith Muir
Director
The Colong Foundation for Wilderness Ltd
Attachments
Name Withheld
Object
Kurrajong , New South Wales
Message
I object to this proposal because it is located next to a World Heritage Area that is environmentally sensitive.

Threatened species will be affected should this proceed and the cost to the economy and to Tourism to the area far outweigh the financial benefits over 30 years.

State Significant Areas should be properly managed by our government departments and due diligence needs to be demonstrated by our politicians particularly those responsible for environmental legal obligations!
Attachments

Pagination

Project Details

Application Number
SSD-4978
Assessment Type
State Significant Development
Development Type
Extractive industries
Local Government Areas
Hawkesbury City
Decision
Approved
Determination Date
Decider
ED

Contact Planner

Name
Colin Phillips