Complaints
Want to lodge a compliance complaint about this project?
Make a Complaint
Enforcements
Official Cautions issued to John Holland and CPB Contractors Pty Ltd
On 3 February 2021, the Department issued (2) Official Cautions to John Holland and CPB Contractors Pty Limited (JHCPB) for failure to submit a report to the Planning Secretary justifying why operational noise mitigation measures identified in the Operational Noise and Vibration Review (ONVR) were not implemented within the required time frame, and detailing the temporary measures that would be implemented until such time as the operational noise mitigation measures identified in the ONVR are implemented. The justification report has since been submitted to the Department.
Penalty Notice issued to CPB Contractors Pty Ltd
On 3 February 2021, the Department issued a $15,000 Penalty Notice to CPB Contractors Pty Ltd (CPB) as a partner in the John Holland and CPB Contractors Pty Ltd joint venture (JHCPB), for failing to implement acoustic treatments for eligible receivers under the Noise Insulation Program (NIP) within the required time frames at the WestConnex M4-M5 Link Rozelle Interchange development. JHCPB have committed additional resourcing to ensure the NIP is implemented as required. The Department will continue to monitor compliance with conditions of approval.
Official Cautions issued to Load Ranger Pty Ltd, Load & Go Pty Ltd, P.L. Tripodi Pty Limited, Attcall Civil Contractors Pty Ltd, Hi-Quality Environmental Services Pty Ltd and Rocktown Pty Ltd (SSI-7485) Inner West LGA
Between 1 and 2 March 2022, the Department issued (6) Official Cautions to Load Ranger Pty Ltd (Load Ranger), Load & Go Pty Ltd (Load & Go), P.L. Tripodi Pty Limited (Tripodi), Attcall Civil Contractors Pty Ltd (Attcall), Hi-Quality Environmental Services Pty Ltd (Hi-Quality) and Rocktown Pty Ltd (Rocktown) for failure to adhere to restrictions on the use of a spoil haulage vehicle route (Route A), on the WestConnex M4-M5 Link Tunnel project (the project). The use of Route A by spoil haulage vehicles on the project is restricted to 7 am to 7 pm to minimise amenity impacts on surrounding residents. Spoil haulage vehicles operating on the project on behalf of Load Ranger, Load & Go, Tripodi, Attcall, Hi-Quality and Rocktown (separately) used Route A prior to 7 am on numerous occasions between June 2019 and May 2020. Since May 2020, additional management measures have been implemented on the project to better prevent and address any use of Route A outside the hours of 7 am to 7pm. The Department will continue to monitor compliance with conditions of approval.
Penalty Notice issued to ResourceCo Material Solutions Pty Ltd (SSI-7485) Inner West LGA
On 1 March 2022, the Department issued a $15,000 Penalty Notice to ResourceCo Material Solutions Pty Ltd (ResourceCo) for failure to adhere to restrictions on the use of a spoil haulage vehicle route (Route A), on the WestConnex M4-M5 Link Tunnel project (the project). The use of Route A by spoil haulage vehicles on the project is restricted to 7 am to 7 pm to minimise amenity impacts on surrounding residents. Spoil haulage vehicles operating on the project on behalf of ResourceCo used Route A prior to 7 am on numerous occasions between November 2019 and April 2020. ResourceCo was advised in November 2019 that its vehicles were using Route A contrary to the restrictions on its use, however its vehicles continued using Route A outside of the approved hours until April 2020. Since May 2020, additional management measures have been implemented on the project to better prevent and address any use of Route A outside the hours of 7 am to 7pm. The Department will continue to monitor compliance with conditions of approval.
Inspections
9/01/2020
10/01/2020
30/01/2020
14/02/2020
28/02/2020
6/03/2020
9/03/2020
12/03/2020
12/03/2020
12/03/2020
17/03/2020
17/03/2020
29/04/2020
29/04/2020
29/04/2020
4/05/2020
27/07/2020
11/09/2020
25/02/2021
26/02/2021
6/05/2021
25/01/2022
28/04/2022
16/06/2022
15/12/2022
18/05/2023
11/10/2023
22/11/2023
13/12/2023
9/04/2024
7/08/2024
28/08/2024
Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.