EPA
Comment
EPA
Comment
Parramatta
,
New South Wales
Message
Attachments
Office of Environment and Heritage
Comment
Office of Environment and Heritage
Comment
Parramatta
,
New South Wales
Message
Attachments
Liverpool City Council
Comment
Liverpool City Council
Comment
Liverpool
,
New South Wales
Message
see attached
Attachments
NSW Trade & Investment (Division of Resource & Energy)
Comment
NSW Trade & Investment (Division of Resource & Energy)
Comment
Hunter Regional Mail Centre
,
New South Wales
Message
Thank you for the opportunity to provide advice on the above matter. This is a response from the New South Wales Department of Trade and Investment - Geological Survey of New South Wales (GSNSW).
The GSNSW has no resource issues to raise in regard to the above matter.
Queries regarding the above information, and future requests for advice in relation to this matter, should be directed to the GSNSW Land Use team at [email protected]
The GSNSW has no resource issues to raise in regard to the above matter.
Queries regarding the above information, and future requests for advice in relation to this matter, should be directed to the GSNSW Land Use team at [email protected]
Endeavour Energy
Comment
Endeavour Energy
Comment
Huntingwood
,
New South Wales
Message
Dear Sir/Madam
Endeavour Energy has reviewed the proposed development for the Bringelly Rd Business Hub at Leppington. We have no objections to the development however have specific comments to make regarding electricity supply.
The development will result in significant additional demand on the existing electrical distribution network. Our preliminary assessment is that the developer will be required to install 2 new 11kV feeders from our Prestons Zone Substation located on Camden Valley Way Prestons.
The exact scope of connection works will be subject to a detailed assessment at the time of application. The developer or their service provider can make application by contacting [email protected].
Please contact me on (02) 9853 5003 should you wish to discuss further.
Regards
Jason Lu
Capacity Planning Manager
Endeavour Energy has reviewed the proposed development for the Bringelly Rd Business Hub at Leppington. We have no objections to the development however have specific comments to make regarding electricity supply.
The development will result in significant additional demand on the existing electrical distribution network. Our preliminary assessment is that the developer will be required to install 2 new 11kV feeders from our Prestons Zone Substation located on Camden Valley Way Prestons.
The exact scope of connection works will be subject to a detailed assessment at the time of application. The developer or their service provider can make application by contacting [email protected].
Please contact me on (02) 9853 5003 should you wish to discuss further.
Regards
Jason Lu
Capacity Planning Manager