Designated Development - Waste Facility

Determined

Asbestos Disposal Area

Western Regional Planning Panel

The proposal is for the disposal of asbestos waste that will be generated by the Wallerawang Power Station Closure Project. It is estimated that about 7,000 cubic metres of asbestos waste would be generated and that requires a landfill of approximately 11,000 cubic metres of capacity.

The new asbestos disposal area is proposed to be within the Wallerawang Ash Repository site to the south of Kerosene Vale Ash Repository and an access road to Sawyers Swamp Creek Ash Dam. The site is within Lot 5 of DP829137 and is on land owned by EnergyAustralia.

The asbestos disposal area is proposed to have a footprint of up to approximately 1.8 hectares. It would comprise of six parallel 250-metre long trenches, each three metres wide and three metres deep. Each trench would be excavated and filled progressively as the need arises.

The trenches would be excavated progressively and would be filled to a depth of about 2.5 metres with bagged or wrapped asbestos waste. This trench-and-fill method would enable the length of open trench to be matched to the volume of asbestos waste being generated by the Wallerawang Power Station Closure Project at any one time.

The Wallerawang Power Station Closure Project is estimated to take approximately two years to implement with the proposed asbestos disposal area to be operational throughout this period.

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
20191025 - FINAL VR1 Determination SOR(3)

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
Completed declaration forms

Council Assessment Report (5)

Council Assessment Report
1. Council Assessment Report
Council Assessment Report
2. Attach 1 - SEAR 1194 - Waste Fac (Asbestos Rep)
Council Assessment Report
3. Attachment 2 - Wang Ash Dam MOD 1_ Consent
Council Assessment Report
6. RtS by EA_V1_PPSWES-12
Council Assessment Report
7. Section 4.16 Response - DA 01619

Other (2)

Notice of Panel Meeting
Advert
Submissions (do not publish)
5. RMS Submission

Links (1)

URL
Audio recording – 2019WES002 – 18 October 2018

Meetings

Public determination meeting

Chaired by: Mr Gordon Kirkby

Project Details

DA number
DA016/19
Planning panel reference number
PPS-2019WES002
Capital investment value
$636,340
Project Address
Lot 5 Of Dp829137, Within The Wallerawang Ash Repository Site To The South Of Kerosene Vale Ash Repository
Lodgement date
Referral date
Local government
Lithgow City Council
Type of matter
DA
Determination outcome
Approved