CIV > $5M - Council interest
Determined
Bega Showground Pavilion
Southern Regional Planning Panel
- Construction of an attached one and two-storey addition to the existing heritage listed Bega Showground Pavilion. The proposed addition will be known as the Bega Showground Community Centre.
- Minor alterations to the existing heritage listed Bega Showground Pavilion.
- Landscaping works, including the construction of a new yarning circle.
- Other minor works as documented in this proposal and the documentation included with the DA submission.
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
PPSSTH-233 - Determination and SOR
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
PPSSTH-233 - Planning Panels Meeting Declarations - combined
Council Assessment Report (1)
Council Assessment Report
2022.453 Development Assessment Report
Attachments to Council Assessment Report (3)
Attachment to assessment report
2022.453 Attachment 1 Current plans of the proposed development
Attachment to assessment report
2022.453 Attachment 3 Additional information submitted by the applicant
Attachment to assessment report
2022.453 Attachment 2 Recommended conditions of consent
Record of Briefing (1)
Record of Briefing
PPSSTH-233 - Record of Briefing and Site Inspection 31.05.23
Project Details
DA
number
2022.453
Planning panel reference number
PPSSTH-233
Capital investment value
$15,499,859
Project Address
Upper Street Bega 2550,Upper Street Bega 2550
Lodgement date
Referral date
Local government
Bega Valley Shire Council
Type of matter
DA
Determination outcome
Approved
Determination Date