Capital Investment Value > $20M and lodged before 1 March 2018

Determined

Concept DA - Khartoum Rd

Sydney North Planning Panel

Approval is sought for a Concept Development Application for the entire development and approval of physical works in Stage 1. The concept Development Application includes the design parameters such as building envelopes, building layout and staging of the future development of the site. The development includes the building envelopes for five commercial offices ranging in height from 29.7m to 44.5m. Four retail and support pavilions to a height of 5m are proposed around a central publicly accessible open space area. Basement parking will be provided for 987 vehicles. The development includes a new public road, two private roads and a pedestrian through site link.
The application also seeks approval for Stage 1 works. The Stage 1 works include the demolition of the existing south-western building, construction of a 10 storey mixed use commercial and retail building with 3 levels of basement car parking, construction of a portion of the internal 14.5m private road connecting to Khartoum Road, construction of a portion of the pedestrian through site link and associated landscaping.
The proposal is integrated development under the Environmental Planning & Assessment Act 1979, as it requires a dewatering license. The relevant approval body is the NSW Office of Water.

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
2018SNH009 Determination & SOR 4 Dec 2019

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
2018SNH009 Panel Declarations 4 Dec 2019

Council Assessment Report (4)

Council Assessment Report
Plans
Council Assessment Report
2018SNH009 Assessment Report
Council Assessment Report
Attachment 1 Draft Conditions
Council Assessment Report
Attachment 2 GTA Water NSW

Other (6)

URL
Audio recording - 4 Dec 2019 - 2018SNH009
Other
2018SNH009 Signed VPA 2 Dec 2019
Other
Applicant Letter agreeing to contributions to RMS
Other
2018SNH009 Resolution 2 Dec 2019
Notice of Panel Meeting
Notice of Public Meeting 4 Dec 2019 Ryde
Other
Record of Briefing 25 July 2018.pdf

Links (1)

URL
Audio recording - 4 Dec 2019 - 2018SNH009

Meetings

Public determination meeting

Chaired by: Mr Peter Debnam

Project Details

DA number
LDA2017/0547
Planning panel reference number
PPS-2018SNH009
Capital investment value
$81,271,195
Project Address
11-17 Khartoum Road, Macquarie Park
Lodgement date
Referral date
Local government
Ryde City Council
Type of matter
DA