Designated Development - Waste Facility

Determined

Dunmore Resource Recovery Redevelopment

Southern Regional Planning Panel

- transfer facility relocation & reorganisation,
- expansion & reconfiguration of existing composting facility,
- relocation of gas flare,
- relocation of existing leachate storage ponds,
- new tunnel composting of organics & associated biofilter,
- reorientation of existing revolve centre & associated car parking,
- upgrade of internal road network & reconfiguration of entry inspection, reallocation of traffic routes & upgrades & relocation of weighbridges,
-earthworks including levelling of site,
- selected tree removal & boundary screen landscaping,
- relocation & expansion of existing utilities, and
- relocation of staff & office facilities, car parking, operational equipment & storage repair areas .

Other (10)

Other
Determination & Statement of Reasons.pdf
Other
Agenda 26 August 2015.pdf
Other
Photomontages.pdf
Other
Architectural Drawnings.pdf
Other
Office of Water.pdf
Other
OEH.pdf
Other
EPA General Terms of Approval.pdf
Other
Addtional information 19 March.pdf
Other
Additional Information.pdf
Other
Council Assessment Report.pdf

Meetings

Public determination meeting

Chaired by: Pam Allan

Project Details

DA number
523/2014
Planning panel reference number
PPS-2015STH001
Capital investment value
$12,560,000
Project Address
Lot 1 Dp 110135, Lot 21 Dp 653009, Lot 1 Dp 419907, 44 &Amp; 58 Buckleys Road Dunmore
Lodgement date
Referral date
Local government
Shellharbour City Council
Type of matter
DA
Determination outcome
Approved
Determination Date