Designated Development - Extractive Industry
Determined
Millers Metal Quarry
Western Regional Planning Panel
Increase extraction limit from 100,000 tonnes per annum to 250,000 tonnes per annum
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
PPSWES-9 Determination and SOR 14 July 2020
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
Completed Panel declaration forms
Council Assessment Report (1)
Council Assessment Report
PPSWES-9 Assessment Report
Attachments to Council Assessment Report (2)
Other (1)
Other
Revised conditions of consent_Bland Shire Council_Final
Project Details
DA
number
DA2020/0004
Planning panel reference number
PPSWES-9
Capital investment value
$150,000
Project Address
331 Wargin Road Wyalong 2671
Lodgement date
Referral date
Local government
Bland Shire Council
Type of matter
DA
Determination outcome
Approved
Determination Date