Section 96(2) Modification to an Approved Concept Masterplan and Staged Residential Subdivision

Sydney Central City Planning Panel

Section 96(2) Modification to an Approved Concept Masterplan and Staged Residential Subdivision which includes the following:

1. Amend the approved Stormwater Management Strategy for Stage 1B with a single on-site stormwater detention tank in lieu of the two approved tanks;

2. Locate the new single tank 5m from the southern boundary instead of up the hill adjacent Road No. 3;

3. Include 34 Salamander Grove in the application and provide a 3m easement to drain stormwater over its eastern boundary; and

4. Amend conditions of consent associated with the modified stormwater works and removal of bio-retention requirement in addition to VPA monetary contribution for bioretention offset.

Other (1)

Other
Record of Briefing Meeting 2017SWC125.pdf

Project Details

DA number
6/2012/JP/C
Planning panel reference number
PPS-2017SWC125
Capital investment value
$55,068,000
Project Address
Lots 1001-1003 Dp 1190982, Mackillop Drive, Baulkham Hills Nsw 2153
Lodgement date
Referral date
Local government
The Hills Shire Council
Type of matter
DA
Determination Date