S4.55(2) Modification Application

Determined

Waste Management Facility - Composting Facility

Hunter & Central Coast Regional Planning Panel

Modification to Composting Technology

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
Determination and Statement of Reasons - PPSHCC-121

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
PPSHCC-121 - panel declarations - combined

Supplementary Council Assessment Report (1)

Supplementary Council Assessment Report
Supplementary memo to determination report

Council Assessment Report (1)

Council Assessment Report
Regional Planning Panel Assessment Report

Attachments to Council Assessment Report (5)

Attachment to assessment report
Attachment E - EPA correspondence
Attachment to assessment report
Attachment D - Acoustic Assessment Report and Supplementary Report
Attachment to assessment report
Attachment C - Revised Odour Assessment Report and Peer Review
Attachment to assessment report
Attachment B - Architectural Plan
Attachment to assessment report
Attachment A - Draft Conditions of consent

Record of Briefing (5)

Record of Briefing
Record of briefing - September 2022 - PPSHCC-121
Record of Briefing
Record of Briefing PPSHCC-121 (002)
Record of Briefing
Record of Briefing - on site briefing PPSHCC-121
Record of Briefing
Applicant Presentation PPSHCC-121
Record of Briefing
Record of Briefing - Kick off - PPSHCC-121

Project Details

DA number
DA/1940/2013/B
Planning panel reference number
PPSHCC-121
Capital investment value
$664,571
Project Address
413 Wilton Road Awaba,367 Wilton Road Awaba
Lodgement date
Referral date
Local government
Lake Macquarie City Council
Type of matter
DA
Determination outcome
Approved
Determination Date