Designated Development - Waste Facility

Determined

Waste Transfer Station

Hunter & Central Coast Regional Planning Panel

Waste Transfer Station

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
Determination PPSHCC-30

Completed Panel Declaration forms (2)

Completed Panel Declaration forms
Updated declaration forms PPSHCC-9
Completed Panel Declaration forms
Completed declaration forms PPSHCC-30

Record of Deferral (1)

Record of deferral
Record of Deferral PPSHCC-30

Council Assessment Report (1)

Council Assessment Report
R5 Mooramba Avenue Tuggerah Waste Transfer Station FINAL REVIEW

Attachments to Council Assessment Report (1)

Attachment – plans
Development Plans - 5 Mooramba Ave TUGGERAH - DA9142019

Record of Briefing (1)

Record of Briefing
Record of Briefing PPSHCC-30

Other (7)

Attachment to supplementary assessment report
New Draft conditionsreasons - ~opment - Central Coast Council
Attachment to supplementary assessment report
12315.5 - DA-REV L
Attachment to supplementary assessment report
180361 - REV E
Attachment to supplementary assessment report
Attachment 1 - Updated Plans - March 2021
Attachment to supplementary assessment report
Attachment 2 - SEARS Compliance Tables - Mar 2021
Attachment to supplementary assessment report
Attachment 3 - Revised Draft conditions reasons
Supplementary assessment report
Supplementary RPP Report - 5 Mooramba Ave Tuggerah PPSHCC-30

Project Details

DA number
DA/914/2019
Planning panel reference number
PPSHCC-30
Capital investment value
$850,000
Project Address
5 Mooramba Avenue Tuggerah 2259
Lodgement date
Referral date
Local government
Central Coast Council
Type of matter
DA
Determination outcome
Refused