  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

The application for MOD 1 proposes to:
- increase the life of the quarry by 10 years,
- allow the importation of ENM material in addition to VENM to the site for processing;
- substitute a 8 ha area of vegetation for 12 ha of rehabilitated land.

Attachments & Resources

Notice of Exhibition (1)

Modification Application (1)

Response to Submissions (2)

Additional Information (8)

Recommendation (4)

Determination (3)

Consolidated Consent (1)

Submissions

Filters
Showing 1 - 11 of 11 submissions
TfNSW
Comment
Chippendale , New South Wales
Message
Additional information is required prior to the determination of the application
Attachments
Biodiversity and Conservation Division
Comment
PARRAMATTA , New South Wales
Message
Please see attached.
Attachments
Crown Lands
Comment
,
Message
A check of the P. F. Formation Statement of Environmental Effects indicates that there is a section of Crown road , within the Project Site Boundary, off the Old Northern Road as shown on Figure 1, Locality Plan. However this figure may be an error as the Project Site Boundary, shown on Figure 2 Proposed Biodiversity Offset and Rehabilitation Strategy, appears to be in more detail and shows the section of Crown road excluded from the Project Site Boundary. If this is the case then Crown Lands has no further comments.
NSW Resources Regulator
Comment
MAITLAND , New South Wales
Message
The Regulator has no comment – there are no active mining titles over the area.
ENVIRONMENT PROTECTION AUTHORITY
Comment
,
Message
The EPA's request for further information is attached
Attachments
Regional NSW - Mining, Exploration & Geoscience
Comment
Maitland , New South Wales
Message
Please see attached document
Attachments
ROADS AND MARITIME SERVICES DIVISION
Comment
PARRAMATTA , New South Wales
Message
The attached document was sent to planning on 6 August 2020
Attachments
Water Group
Comment
,
Message
The Department of Planning, Industry and Environment - Water and the Natural Resources Access Regulator (NRAR) have reviewed the proposal and have no comments.
THE HILLS SHIRE COUNCIL
Comment
Norwest , New South Wales
Message
Letter from The Hills Shire Council
Attachments
Natural Resources Access Regulator
Comment
Wollongong , New South Wales
Message
This is a pre-approval major project referral which must be sent to the Landuse Enquiries team at [email protected] for a coordinated response with DPIE Water rather than direct to NRAR.
ENVIRONMENT PROTECTION AUTHORITY
Comment
,
Message
EPA response is attached.
Attachments

Pagination

Project Details

Application Number
MP06_0104-Mod-1
Main Project
MP06_0104
Assessment Type
SSD Modifications
Development Type
Extractive industries
Local Government Areas
The Hills Shire
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Jessie Evans