Mod 5 - Cooling System & Car Park Access
City of Sydney
Current Status: Determination
Attachments & Resources
Application (21)
DGRs (1)
Agency Submissions (3)
Determination (2)
Submissions
Showing 1 - 1 of 1 submissions
Shane Schneider
Comment
Shane Schneider
Comment
North Sydney
,
New South Wales
Message
RMS Comments for the proposal are:
1) RMS/Transport for NSW comments provided to earlier versions of the application still apply.
2) Sections 4.1, 4.2 and 4.2.2 of Appendix H refer to a proposed street layout that is not described completely accurately. Approval has been provided for the partial closure of Shelley Street westbound from Sussex Street only for the construction period of Wynyard Walk. Any permanent closure of Shelly Street is subject to additional requirements and approval that has not yet occurred. The permanent configuration of the intersection of Sussex Street/Shelley Street will be determined within that process.
3) The intersection designs, pedestrian/traffic facilities, road configuration and infrastructure for the sections of Erskine Street and Lime Street, between Sussex Street and Barangaroo South should be reviewed and upgraded to provide suitable access to and from the development proposal.
4) Proposed traffic light intersections will require approval from RMS.
1) RMS/Transport for NSW comments provided to earlier versions of the application still apply.
2) Sections 4.1, 4.2 and 4.2.2 of Appendix H refer to a proposed street layout that is not described completely accurately. Approval has been provided for the partial closure of Shelley Street westbound from Sussex Street only for the construction period of Wynyard Walk. Any permanent closure of Shelly Street is subject to additional requirements and approval that has not yet occurred. The permanent configuration of the intersection of Sussex Street/Shelley Street will be determined within that process.
3) The intersection designs, pedestrian/traffic facilities, road configuration and infrastructure for the sections of Erskine Street and Lime Street, between Sussex Street and Barangaroo South should be reviewed and upgraded to provide suitable access to and from the development proposal.
4) Proposed traffic light intersections will require approval from RMS.
Pagination
Project Details
Application Number
MP10_0023-Mod-5
Main Project
MP10_0023
Assessment Type
Part3A Modifications
Development Type
Residential & Commercial
Local Government Areas
City of Sydney
Decision
Approved
Determination Date
Decider
Dir(Metro/Reg-N)
Contact Planner
Name
Sara
Roach
Related Projects
MP10_0023-Mod-1
Determination
Part3A Modifications
Mod 1 - Design Changes
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-2
Withdrawn
Part3A Modifications
Mod 2 - Remediation
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-3
Determination
Part3A Modifications
Mod 3 - Further Design Changes
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-4
Determination
Part3A Modifications
Mod 4 - Temporary Concrete Batching Plant
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-5
Determination
Part3A Modifications
Mod 5 - Cooling System & Car Park Access
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-6
Determination
Part3A Modifications
Mod 6 - Design Refinements
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-7
Determination
Part3A Modifications
Mod 7 - Further Design Refinements
Hickson Road Sydney New South Wales Australia 2000
MP10_0023-Mod-8
Determination
Part3A Modifications
Mod 8 - Public Domain Changes
Hickson Road Sydney New South Wales Australia 2000