  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

Changes to the mine layout for the initial scandium mining phase.

Attachments & Resources

Notice of Exhibition (3)

Early Consultation (1)

Modification Application (9)

Response to Submissions (1)

Agency Advice (7)

Submissions

Filters
Showing 1 - 4 of 4 submissions
Daniel Mendes
Support
Chatswood , New South Wales
Message
I support the project
Desmond Ward
Comment
FIFIELD , New South Wales
Message
I wish to raise my concerns regarding the proponent's statement about seepage from the tailings in mod 8. Seepage during or after the project life going into the open cut pits that the proponent has already stated will result in inflows from the aquifer pose an unacceptable risk of contamination of the aquifer.

Wilmatha Road
The Wilmatha Rd must be upgraded to a much higher standard and sealed as in some sections between Fifield and the mine site, is narrow, poorly aligned with large gum trees close to the road. At present passing wide loads is almost impossible. Leaving this road unsealed will mean dust will also pose a much higher risk.
PARKES SHIRE COUNCIL
Comment
PARKES , New South Wales
Message
Attachments
FORBES SHIRE COUNCIL
Support
FORBES , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
DA374-11-00-Mod-8
Main Project
DA374-11-00
Assessment Type
SSD Modifications
Development Type
Minerals Mining
Local Government Areas
Forbes Shire

Contact Planner

Name
Noshin Monshi