Skip to main content
Back to Main Project

SSD Modifications

Response to Submissions

Modification 3 Realignment of Stormwater Channel

Wollongong City

Current Status: Response to Submissions

Interact with the stages for their names

  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

Realign the Eastern Gully Stormwater Diversion and extend the site over the aquired easement. The change to open channel gravity drainage would remove the need for a pond outlet. No change to the landfill capacity or waste input rates.

Attachments & Resources

Notice of Exhibition (1)

Modification Application (2)

Response to Submissions (1)

Agency Advice (4)

Additional Information (1)

Submissions

Filters
Showing 1 - 2 of 2 submissions
Endeavour Energy
Comment
Parramatta , New South Wales
Message
Please refer to the attached documents.
Attachments
Wollongong City Council
Comment
WOLLONGONG , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
MP11_0094-Mod-3
Main Project
MP11_0094
Assessment Type
SSD Modifications
Development Type
Waste collection, treatment and disposal
Local Government Areas
Wollongong City

Contact Planner

Name
Jonah Naja