State Significant Development

Determination

Mt Piper Battery Energy Storage System.

Lithgow City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Development of a standalone 500 MW battery storage system and ancillary infrastructure.

Attachments & Resources

Request for SEARs (1)

SEARs (12)

EIS (17)

Exhibition (1)

Response to Submissions (2)

Agency Advice (23)

Additional Information (4)

Determination (3)

Approved Documents

There are no post approval documents available

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

There are no inspections for this project.

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 41 - 41 of 41 submissions
Lithgow City Council
Support
Lithgow , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
SSD-50903958
Assessment Type
State Significant Development
Development Type
Electricity supply
Local Government Areas
Lithgow City
Decision
Approved
Determination Date
Decider
Executive Director

Contact Planner

Name
Carl Dumpleton