Skip to main content
Back to Main Project

SSD Modifications

Determination

Wilga Park Power Station (MOD 7)

Narrabri Shire

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Assessment
  3. Recommendation
  4. Determination

The installation of a separation vessel and associated water storage tank, piping and instrumentation to manage water in the existing buried gas pipeline.

Attachments & Resources

Modification Application (1)

Determination (3)

Consolidated Consent (1)

Project Details

Application Number
MP07_0023-Mod-7
Main Project
MP07_0023
Assessment Type
SSD Modifications
Development Type
Electricity generation - Other
Local Government Areas
Narrabri Shire
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Iwan Davies