SSD Modifications
Prepare Mod Report
Eastern Creek Data Centre - Mod 2 - Power consumption increase
Blacktown
Current Status: Prepare Mod Report
Interact with the stages for their names
- Prepare Mod Report
- Assessment
- Recommendation
- Determination
Want to stay updated on this project?
The modification seeks approval for an increase in the overall power consumption of the development (to 70.2 megawatts), along with corresponding plant and equipment changes (including additional back-up generators).
Project Details
Application Number
SSD-21342738-Mod-2
Main Project
SSD-21342738
Assessment Type
SSD Modifications
Development Type
Warehouse or distribution centres
Local Government Areas
Blacktown