  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

• Reduction in number of apartments from 327 to 317
• Revised dwelling mix & associated internal layout refinements
• Facade and landscaping alterations
• Addition of 13 residential car parking spaces and removal of 1 retail car parking space

Attachments & Resources

Modification Application (13)

Response to Submissions (3)

Agency Advice (1)

Additional Information (5)

Recommendation (2)

Determination (4)

Submissions

Filters
Showing 1 - 5 of 5 submissions
ENVIRONMENT PROTECTION AUTHORITY
Comment
Sydney , New South Wales
Message
Hi Karl,
Please find attached the EPA's comments on Barangaroo - R4A Residential Building - MOD 1 - Building R4A design & car parking changes (SSD-6964-Mod-1).
Kind regards,
Mark
Attachments
ROADS AND MARITIME SERVICES DIVISION
Support
PARRAMATTA , New South Wales
Message
No objections.
Attachments
TRANSPORT FOR NSW
Comment
Chippendale , New South Wales
Message
A copy of the TfNSW resposne letter is attached.
Attachments
City of Sydney
Object
SYDNEY , New South Wales
Message
Dear Karl

Please find attached the City's objection to the proposed modifications.

David Zabell
Attachments
David and Lorraine Sketch
Comment
MILLERS POINT , New South Wales
Message
Modification Application R4A (SSD6964-Mod-1) and R4B (SSD6965-Mod-1)
Thank you for your notification dated 29 October 2019 regarding the proposed modifications.
While we have had limited time to review all details of each modification, in principal we have no objections.
We note that the Development Consents for Building R4A and Building R4B dated 7 September 2017 (Part D During Construction) limits the hours of construction to between 7am and 7pm, Mondays to Fridays and 7am and 5pm Saturdays.
We again implore the Department to ensure that the approved hours of construction are adhered to and that any allowed works undertaken outside these hours use low-noise equipment, noise reduction barriers, curtains and attenuating devices to minimise disturbances to the community.
We have for the second time this year suffered sleep deprivation because of overnight low frequency noise from the use of de-watering pumps on the One Sydney Harbour site.

David and Lorraine Sketch

Pagination

Project Details

Application Number
SSD-6964-Mod-1
Main Project
SSD-6964
Assessment Type
SSD Modifications
Development Type
Residential & Commercial
Local Government Areas
City of Sydney
Decision
Approved
Determination Date
Decider
Executive Director

Contact Planner

Name
Karl Fetterplace