Skip to main content
Back to Main Project

SSD Modifications

Determination

MOD 4 - Administrative changes (CWO)

Mid-Western Regional

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Assessment
  3. Recommendation
  4. Determination

Administrative changes related to construction of the Central West Orana Transmission Line

Attachments & Resources

Modification Application (1)

Determination (2)

Consolidated Consent (1)

Project Details

Application Number
SSD-6764-Mod-4
Main Project
SSD-6764
Assessment Type
SSD Modifications
Development Type
Coal Mining
Local Government Areas
Mid-Western Regional
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
sarah cavaleri
Phone