Current Status: Determination
Attachments & Resources
Application (1)
EA (8)
Response to Submissions (2)
Recommendation (1)
Determination (2)
Submissions
Showing 1 - 11 of 11 submissions
Airservices Australia
Comment
Airservices Australia
Comment
Tullamarine
,
Victoria
Message
Given the height of the transmission line is over 100m lower than the wind farm's blade tip height, and since the wind farm development did not impact Airservices airspace procedures or CNS facilities (see attached), an assessment is not required due to no expected impact from the proposed transmission line.
Civil Aviation Safety Authority
Comment
Civil Aviation Safety Authority
Comment
Canberra
,
Australian Capital Territory
Message
See attached.
Attachments
Inverell Shire Council
Comment
Inverell Shire Council
Comment
Inverell
,
New South Wales
Message
See attached.
Attachments
NSW Rural Fire Service
Comment
NSW Rural Fire Service
Comment
Granville
,
New South Wales
Message
Please see attached.
Attachments
Department of Industry - Division of Resources and Energy
Comment
Department of Industry - Division of Resources and Energy
Comment
Maitland
,
New South Wales
Message
Please see attached.
Attachments
Roads and Maritime Services
Comment
Roads and Maritime Services
Comment
Grafton
,
New South Wales
Message
Please see attached.
Attachments
Department of Primary Industries
Comment
Department of Primary Industries
Comment
Sydney
,
New South Wales
Message
Please see attached.
Attachments
Office of Environment and Heritage
Comment
Office of Environment and Heritage
Comment
Coffs Harbour
,
New South Wales
Message
Please see attached.
Attachments
Glen Innes Severn Council
Comment
Glen Innes Severn Council
Comment
Glen Innes
,
New South Wales
Message
Please see attached.
Attachments
Environment Protection Authority
Comment
Environment Protection Authority
Comment
Armidale
,
New South Wales
Message
Please see attached.
Attachments
Glen Innes Severn Council
Comment
Glen Innes Severn Council
Comment
Glen Innes
,
New South Wales
Message
See attached.
Attachments
Pagination
Project Details
Application Number
MP10_0160-Mod-4
Main Project
MP10_0160
Assessment Type
Part3A Modifications
Development Type
Electricity Generation - Wind
Local Government Areas
Glen Innes Severn
Decision
Approved
Determination Date
Decider
Director
Related Projects
MP10_0160-Mod-1
Withdrawn
Part3A Modifications
Mod 1 - Transmission Changes
Suite 2, Level 23 201 Elizabeth Street Sydney New South Wales Australia 2000
MP10_0160-Mod-2
Determination
Part3A Modifications
Mod 2 - Noise & Vegetation Clearing
Suite 2, Level 23 201 Elizabeth Street Sydney New South Wales Australia 2000
MP10_0160-Mod-3
Determination
Part3A Modifications
Mod 3 - Design Changes
Suite 2, Level 23 201 Elizabeth Street Sydney New South Wales Australia 2000
MP10_0160-Mod-4
Determination
Part3A Modifications
Mod 4 - Grid Connection
Suite 2, Level 23 201 Elizabeth Street Sydney New South Wales Australia 2000
MP10_0160-Mod-5
Determination
Part3A Modifications
Mod 5 - Substation Subdivision
Suite 2, Level 23 201 Elizabeth Street Sydney New South Wales Australia 2000
MP10_0160-Mod-6
Determination
Part3A Modifications
Mod 6 - Stage 2 Turbine Changes
Suite 2, Level 23 201 Elizabeth Street Sydney New South Wales Australia 2000