Skip to main content
Back to Main Project

Part3A Modifications

Determination

Mod 8 - Administrative Change

Shellharbour City

Current Status: Determination

Attachments & Resources

Request for SEARs (3)

EA (25)

Agency Submissions (4)

Response to Submissions (7)

Determination (3)

Submissions

Filters
Showing 1 - 5 of 5 submissions
Roads and Maritime Services
Comment
Port Kembla , New South Wales
Message
Dear NSW Planning,

In response to your correspondence, I wish to confirm that the
Maritime Division of Roads and Maritime Services (RMS) have no
objection to this proposal, assessed on the grounds of impact to
navigation.

In providing this advice RMS bears no responsibility in relation to
the suitability of the site for the proposed vessel berthing plan with
specific regard to sea room and water depth.

Kind Regards
Deon Voyer
Manager Operations
Maritime Operations & Compliance | South
rms.nsw.gov.au/maritime
Every journey matters

Roads and Maritime Services
Level 2, 91 Foreshore Road PORT KEMBLA NSW 2505
Environment Protection Authority
Comment
Wollongong , New South Wales
Message
Submission attached.
Attachments
Office of Environment and Heritage
Comment
Queanbeyan , New South Wales
Message
See attached.
Attachments
Roads and Maritime Services
Comment
xxxx , New South Wales
Message
Submissions attached.
Attachments
Shellharbour City Council
Comment
Shellharbour City Centre , New South Wales
Message
Please see attached.
Attachments

Pagination

Project Details

Application Number
DA95/133-Mod-8
Main Project
DA95/133
Assessment Type
Part3A Modifications
Development Type
Marinas
Local Government Areas
Shellharbour City
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Michelle Niles