MOD 8 Mamre Road Sequence 1B upgrade extension

Penrith

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Assessment
  3. Recommendation
  4. Determination

This modification seeks to amend Condition B11 of Development Consent SSD-9522, to extend the completion date for the construction of the Mamre Road Sequence 1B upgrade from 31 December 2025 to 30 June 2027.