Modification 10 is seeking to optimise the CHPP and workshop facilities at Rix's Creek North.
Attachments & Resources
Notice of Exhibition (1)
Early Consultation (1)
Modification Application (4)
Response to Submissions (2)
Agency Advice (6)
Amendments (2)
Additional Information (4)
Determination (2)
Consolidated Consent (1)
Submissions
Showing 41 - 60 of 61 submissions
Ben White
Support
Ben White
Support
NORTH ROTHBURY
,
New South Wales
Message
I am in support of the Rix's creek Mod 10. It would ensure employment for myself, and support my families future in the local area. I have worked for Bloomfield group at Rix's Creek for 8 years, and I am very proud to be working for the only Australian owned and operated mine in the valley, employing approximately 600 local people full time and thousands of contractors directly and indirectly.
This employment has a huge flow on affect in the community supporting local businesses. Rix's creek regularly support local sporting teams and organisations. Also donating to local charities including the Westpac rescue helicopter.
Please approve the Mod 10 for Rix's creek for my future, my families future, for the local area's future.
This employment has a huge flow on affect in the community supporting local businesses. Rix's creek regularly support local sporting teams and organisations. Also donating to local charities including the Westpac rescue helicopter.
Please approve the Mod 10 for Rix's creek for my future, my families future, for the local area's future.
Name Withheld
Support
Name Withheld
Support
Barnsley
,
New South Wales
Message
I support Rix's Creek North - Modification 10.
The environmental assessments conducted for MOD 10 have confirmed that the proposed changes will have a minimal impact on the environment. These modifications will occur entirely within areas previously approved for disturbance. Additionally, mining operations following these infrastructure updates will continue as they are now, with no alterations to the annual production levels.
The environmental assessments conducted for MOD 10 have confirmed that the proposed changes will have a minimal impact on the environment. These modifications will occur entirely within areas previously approved for disturbance. Additionally, mining operations following these infrastructure updates will continue as they are now, with no alterations to the annual production levels.
Michael Hanly
Support
Michael Hanly
Support
MUSWELLBROOK
,
New South Wales
Message
I am in support of the Rix's creek Mod 10 because it would ensure employment for me and support my families future in the local area. I have worked for Bloomfield Rixs creek for 8 years and I am very proud to be working for the only Australian owned mine in the valley, employing approximately 600 local people full time and thousands of contractors directly and indirectly. This employment has a huge flow on affect in the community supporting local shops, mechanics, hair dressers, so on and so on. Rix's creek regularly support local sporting teams and organisations. Donating to local charities including the Westpac rescue helicopter. Please approve the Mod 10 for Rix's creek for my future, my families future, for everyone's future.
Name Withheld
Support
Name Withheld
Support
SINGLETON
,
New South Wales
Message
Modification 10 should be non-controversial. Its inclusions are primarily in relation to upgrading existing aging infrastructure or efficiency improvements. All proposed modifications are within the existing approved footprint of the mine. Rix's Creek Mine has been operating for decades, provides secure employment for hundreds of local people and has an excellent record of care for these people and the broader community.
Sharon Turnbull
Support
Sharon Turnbull
Support
RUTHERFORD
,
New South Wales
Message
I have been part of a family that has been supported by the mining industry most of my life. I have parents whose business was supported by mining, a husband whose work is supported by the mining industry, two brothers and myself who directly work in mining, and my son and son-in-law who work in mining-related industries. We need this project to keep jobs and income flowing through the Hunter Valley community and keep our towns alive and thriving.
Simon Allan
Support
Simon Allan
Support
SEDGEFIELD
,
New South Wales
Message
My family and I support the Rix's Creek North - Modification 10 project as The Bloomfield Group is a massive supporter of the local community both in the Singleton and Maitland areas, along with employing many local residents which gives a positive future to many families and business within the Hunter Shire.
Brett Lewis
Support
Brett Lewis
Support
MEREWETHER
,
New South Wales
Message
The proposed project modifications outlined in Mod10 seek to make the Rix's Creek project more economically and operationally resilient without material changes to its current environmental impacts. If MOD10 is approved, the Rix's Creek project will provide a more secure workplace that directly supports hundreds of Hunter residents and their families and many more indirectly, while also providing the opportunity for improved environmental outcomes.
Larissa Weir
Support
Larissa Weir
Support
MEREWETHER
,
New South Wales
Message
As a proud employee of the Bloomfield Group and an advocate for the positive impact that mining has on our communities and our customers, I am pleased to support Rix’s Creek North - Modification 10 (MOD 10). This proposal includes valuable upgrades such as new processing equipment and tailings dewatering facilities at the CHPP, which will help reduce our reliance on tailings dams. The extension of the workshop, the addition of an in-pit rock crushing facility, and the replacement of the substation with a new switching station are all positive steps for improving our operations. Additionally, the in-pit disposal of heavy vehicle waste tyres and concrete materials reflects our commitment to responsible waste management. These changes will enhance our efficiency and have a positive impact on our employees and the local community. I am confident that these improvements will support our ongoing efforts to maintain high standards and benefit both our team and the community.
Rodney Peet
Support
Rodney Peet
Support
EAST MAITLAND
,
New South Wales
Message
I am writing to express my support for the proposed modification to amend the mining plans, submitted by Rix's Creek.
As an employee of the Bloomfield Group, I have seen demonstrated our commitment to responsible mining practices and our dedication to environmental stewardship. The proposed modification aligns with these demonstrated values, aiming to optimise our operations while ensuring minimal environmental impact.
The amendment seeks to enhance some infrastructure changes that exist wholly within previously approved disturbance areas. The modification request does not change our annual production, and environmental assessments have confirmed that the proposed changes will result in minimal environmental impact.
Our company has a proven track record of adhering to regulatory guidelines and implementing best practices in mining operations. The proposed modification reflects our proactive approach to continuous improvement and our commitment to adapting to evolving industry standards.
In conclusion, I believe that approving this modification will not only benefit our operations but also contribute positively to the local economy and environment. I urge the Department of Planning to consider our submission favourably, knowing that it is backed by thorough assessments, expertise, and a genuine desire to uphold the highest standards in mining.
Thank you for considering my input and for your dedication to ensuring responsible development in our community.
As an employee of the Bloomfield Group, I have seen demonstrated our commitment to responsible mining practices and our dedication to environmental stewardship. The proposed modification aligns with these demonstrated values, aiming to optimise our operations while ensuring minimal environmental impact.
The amendment seeks to enhance some infrastructure changes that exist wholly within previously approved disturbance areas. The modification request does not change our annual production, and environmental assessments have confirmed that the proposed changes will result in minimal environmental impact.
Our company has a proven track record of adhering to regulatory guidelines and implementing best practices in mining operations. The proposed modification reflects our proactive approach to continuous improvement and our commitment to adapting to evolving industry standards.
In conclusion, I believe that approving this modification will not only benefit our operations but also contribute positively to the local economy and environment. I urge the Department of Planning to consider our submission favourably, knowing that it is backed by thorough assessments, expertise, and a genuine desire to uphold the highest standards in mining.
Thank you for considering my input and for your dedication to ensuring responsible development in our community.
Steven Vickers
Support
Steven Vickers
Support
SUNSHINE
,
New South Wales
Message
I am an employee of the Bloomfield Group and am writing in support of Rix’s Creek North – Modification 10.
The significant aims of this modification are to:
• Deliver operational efficiencies which ensure the business remains competitive into the future and reduce resource consumption,
• Provide a system for tailings dewatering, allowing for in pit disposal and reducing reliance on tailings storage facilities.
The project has been designed to maximise benefits and minimise potential environmental and social impacts and this is evident through:
• construction only in areas previously disturbed,
• minor increases in noise levels that are not discernible to the average listener (through the strategic placement of equipment and installation of sound reduction measures such as cladding of buildings), and
• diligent management of waste to ensure minimal long term environmental impacts.
The approval of this project will result in additional expenditure in the region during construction and allow the Bloomfield team to continue to work safely and productively within the community.
The significant aims of this modification are to:
• Deliver operational efficiencies which ensure the business remains competitive into the future and reduce resource consumption,
• Provide a system for tailings dewatering, allowing for in pit disposal and reducing reliance on tailings storage facilities.
The project has been designed to maximise benefits and minimise potential environmental and social impacts and this is evident through:
• construction only in areas previously disturbed,
• minor increases in noise levels that are not discernible to the average listener (through the strategic placement of equipment and installation of sound reduction measures such as cladding of buildings), and
• diligent management of waste to ensure minimal long term environmental impacts.
The approval of this project will result in additional expenditure in the region during construction and allow the Bloomfield team to continue to work safely and productively within the community.
Name Withheld
Support
Name Withheld
Support
WYEE
,
New South Wales
Message
I believe this Modification will help sustain the economic benefits the Rix's Creek Mine brings to the community.
Andrew Nicholas
Support
Andrew Nicholas
Support
WINDELLA
,
New South Wales
Message
I support this proposed Modification for Rix's Creek North.
Ben Kleinschafer
Support
Ben Kleinschafer
Support
EAST BRANXTON
,
New South Wales
Message
I support the project being approved. The project does not include disturbing any new areas, and has very minimal environmental impact. Therefore the project has an overall positive impact on the community providing ongoing job surety for many hundred employees, contractors and others.
Name Withheld
Support
Name Withheld
Support
East Maitland
,
New South Wales
Message
To Whom It May Concern,
I support this modification to the Project. The modifications have minimal environmental effect and make improvements to the operations.
Kind Regards.
I support this modification to the Project. The modifications have minimal environmental effect and make improvements to the operations.
Kind Regards.
Name Withheld
Support
Name Withheld
Support
LAMBTON
,
New South Wales
Message
I strongly support the project as I believe the modifications will improve operations efficiency and reduce volume of material going into tailing dams. I believe that all these will make the site operations more resilient, which in turn will contribute to the economic prosperity of the communities that rely on the Rixs Creek Mine staying in business
Name Withheld
Support
Name Withheld
Support
KOTARA
,
New South Wales
Message
It will ensure employment and provide employment stability for the surrounding community. It will also provide patronage of local businesses by the employee's.
Renata Roberts
Support
Renata Roberts
Support
MEREWETHER
,
New South Wales
Message
I am writing to express my full support for the proposed modification to amend our mining plans, submitted by Rix's Creek.
As a dedicated employee of the Bloomfield Group, I have witnessed firsthand our commitment to responsible mining practices and our unwavering dedication to environmental stewardship. The proposed modification aligns perfectly with these values, aiming to optimise our operations while ensuring minimal environmental impact.
The amendment seeks to enhance some infrastructure changes that exist wholly within previously approved disturbance areas. The modification request does not change our annual production, and environmental assessments have confirmed that the proposed changes will result in minimal environmental impact.
Our company has a proven track record of adhering to regulatory guidelines and implementing best practices in mining operations. The proposed modification reflects our proactive approach to continuous improvement and our commitment to adapting to evolving industry standards.
In conclusion, I firmly believe that approving this modification will not only benefit our operations but also contribute positively to the local economy and environment. I urge the Department of Planning to consider our submission favourably, knowing that it is backed by thorough assessments, expertise, and a genuine desire to uphold the highest standards in mining.
Thank you for considering my input and for your dedication to ensuring responsible development in our community.
As a dedicated employee of the Bloomfield Group, I have witnessed firsthand our commitment to responsible mining practices and our unwavering dedication to environmental stewardship. The proposed modification aligns perfectly with these values, aiming to optimise our operations while ensuring minimal environmental impact.
The amendment seeks to enhance some infrastructure changes that exist wholly within previously approved disturbance areas. The modification request does not change our annual production, and environmental assessments have confirmed that the proposed changes will result in minimal environmental impact.
Our company has a proven track record of adhering to regulatory guidelines and implementing best practices in mining operations. The proposed modification reflects our proactive approach to continuous improvement and our commitment to adapting to evolving industry standards.
In conclusion, I firmly believe that approving this modification will not only benefit our operations but also contribute positively to the local economy and environment. I urge the Department of Planning to consider our submission favourably, knowing that it is backed by thorough assessments, expertise, and a genuine desire to uphold the highest standards in mining.
Thank you for considering my input and for your dedication to ensuring responsible development in our community.
Isaac Lumley
Support
Isaac Lumley
Support
BELMONT
,
New South Wales
Message
1. Enhanced Operational Efficiency
Upgraded CHPP Facilities: The installation of new processing equipment on the Run of Mine (ROM) stockpile areas and at the Rix's Creek North CHPP will significantly enhance the efficiency of coal handling and preparation processes. This upgrade will streamline operations, reduce downtime, and improve overall productivity.
In-Pit Rock Crushing Facility: Utilizing rock materials onsite through an in-pit rock crushing facility will decrease transportation costs and associated environmental impacts. It will also ensure a steady supply of crushed rock material for ongoing operations.
2. Environmental Benefits
Tailings Dewatering Facilities: By reducing the reliance on tailings dams through the installation of tailings dewatering facilities, the project will minimize potential environmental risks associated with tailings storage. This is a proactive step towards more sustainable waste management practices.
Waste Disposal in-Pit: The disposal of heavy vehicle waste tyres and waste concrete materials in-pit will help in recycling and reusing waste materials, thereby reducing the environmental footprint of the mine.
3. Economic Advantages
Job Creation and Retention: The development and modification of existing facilities will create new job opportunities during the construction phase and maintain existing jobs in the long term. This supports the local economy and provides stability for the workforce.
Cost Savings: The new thickener and other improvements in the CHPP facilities will lead to cost savings in the processing of coal, making the operation more economically viable and competitive in the market.
4. Infrastructure Improvements
New Substation and Switching Station: Replacing the existing substation and installing a new switching station will enhance the reliability and safety of the mine's electrical infrastructure. This ensures a stable power supply, which is crucial for uninterrupted operations.
Workshop Extension: Extending the workshop will provide additional space for maintenance and repair activities, ensuring that machinery and equipment are kept in optimal condition, thus reducing downtime and maintenance costs.
5. Regulatory Compliance and Safety
Administrative Changes: Minor administrative changes can lead to improved regulatory compliance and operational transparency. Ensuring that all modifications meet current regulations and safety standards protects both the workforce and the surrounding community.
6. Sustainable Development
Thickener Installation: The new thickener installation is an essential step towards sustainable water management. It will enable better management of water resources, reducing water consumption and promoting the recycling of water within the processing plant.
Upgraded CHPP Facilities: The installation of new processing equipment on the Run of Mine (ROM) stockpile areas and at the Rix's Creek North CHPP will significantly enhance the efficiency of coal handling and preparation processes. This upgrade will streamline operations, reduce downtime, and improve overall productivity.
In-Pit Rock Crushing Facility: Utilizing rock materials onsite through an in-pit rock crushing facility will decrease transportation costs and associated environmental impacts. It will also ensure a steady supply of crushed rock material for ongoing operations.
2. Environmental Benefits
Tailings Dewatering Facilities: By reducing the reliance on tailings dams through the installation of tailings dewatering facilities, the project will minimize potential environmental risks associated with tailings storage. This is a proactive step towards more sustainable waste management practices.
Waste Disposal in-Pit: The disposal of heavy vehicle waste tyres and waste concrete materials in-pit will help in recycling and reusing waste materials, thereby reducing the environmental footprint of the mine.
3. Economic Advantages
Job Creation and Retention: The development and modification of existing facilities will create new job opportunities during the construction phase and maintain existing jobs in the long term. This supports the local economy and provides stability for the workforce.
Cost Savings: The new thickener and other improvements in the CHPP facilities will lead to cost savings in the processing of coal, making the operation more economically viable and competitive in the market.
4. Infrastructure Improvements
New Substation and Switching Station: Replacing the existing substation and installing a new switching station will enhance the reliability and safety of the mine's electrical infrastructure. This ensures a stable power supply, which is crucial for uninterrupted operations.
Workshop Extension: Extending the workshop will provide additional space for maintenance and repair activities, ensuring that machinery and equipment are kept in optimal condition, thus reducing downtime and maintenance costs.
5. Regulatory Compliance and Safety
Administrative Changes: Minor administrative changes can lead to improved regulatory compliance and operational transparency. Ensuring that all modifications meet current regulations and safety standards protects both the workforce and the surrounding community.
6. Sustainable Development
Thickener Installation: The new thickener installation is an essential step towards sustainable water management. It will enable better management of water resources, reducing water consumption and promoting the recycling of water within the processing plant.
Greg Hurney
Support
Greg Hurney
Support
THORNTON
,
New South Wales
Message
The Australian owned Bloomfield Group has been a long term mining company within the NSW coal industry. It has helped to unlock the natural resources of the state for the benefit of all Australians. It has provided jobs and prosperity to its employees and the communities within which it operates. The Bloomfield Group has always taken seriously its responsibility to protect the environment and has been a generous and responsible member of the local community. I fully support The Bloomfield Group and its Rix's Creek North - Mod 10 application.
David Steel
Support
David Steel
Support
FARLEY
,
New South Wales
Message
This project will provide ongoing employment for local workers, business opportunities for local suppliers and royalties for the state of NSW.
This organisation has a demonstrated record of responsible environmental management including water management and rehabilitation of mined areas.
This organisation has a demonstrated record of responsible environmental management including water management and rehabilitation of mined areas.
Pagination
Project Details
Application Number
MP08_0102-Mod-10
Main Project
MP08_0102
Assessment Type
SSD Modifications
Development Type
Coal Mining
Local Government Areas
Singleton Shire
Decision
Approved
Determination Date
Decider
Director
Related Projects
MP08_0102-Mod-1
Determination
SSD Modifications
Mod 1
Glennies Creek, New South Wales, Australia
MP08_0102-Mod-2
Determination
SSD Modifications
Mod 2
Glennies Creek, New South Wales, Australia
MP08_0102-Mod-3
Determination
SSD Modifications
Mod 3
Glennies Creek, New South Wales, Australia
MP08_0102-Mod-4
Determination
SSD Modifications
Mod 4
Glennies Creek, New South Wales, Australia
MP08_0102-Mod-5
Determination
SSD Modifications
Mod 5
Glennies Creek, New South Wales, Australia
MP08_0102-Mod-6
Determination
SSD Modifications
Mod 6
Glennies Creek, New South Wales, Australia
MP08_0102-Mod-7
Determination
SSD Modifications
Mod 7
Singleton New South Wales Australia 2330
MP08_0102-Mod-8
Determination
SSD Modifications
Mod 8
Glennies Creek New South Wales Australia
MP08_0102-Mod-9
Determination
SSD Modifications
Rix's Creek North Mine - Landform & Blasting Frequency Modification
Bridgman Road, Singleton, Nsw 2330
MP08_0102-Mod-10
Determination
SSD Modifications
Rix's Creek North - Mod 10 - Minor Optimisation to CHPP
Bridgman Road, Singleton, Nsw 2330