Skip to main content
Back to Main Project

SSI Modifications

Determination

Sydney CBD Light Rail - Mod 5 - Randwick Noise Mitigation

Inner West

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare Mod Report
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Transport for NSW is requesting an administrative modification to change the timing requirments of condition of approval B13.

Attachments & Resources

Application (1)

Determination (3)

Project Details

Application Number
SSI-6042-MOD-5
Main Project
SSI-6042
Assessment Type
SSI Modifications
Development Type
Rail transport facilities
Local Government Areas
Inner West
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Lisa Mitchell