Environment Protection Authority
Comment
Environment Protection Authority
Comment
Armidale
,
New South Wales
Message
The EPA has reviewed the Hillgrove Mines Pty Ltd Environmental Assessment for Modification 3 to DA98/00802. The EPA wishes to advise that it has no objection to the proposed modification of condition 4 of the consent to permit the continuation of mining at the site until 31 December 2019. As the proponent contends that no additional environmental impacts beyond those considered previously in the assessment of DA98/00802 will occur, the EPA does not believe that further modifications to the consent conditions (beyond that proposed for condition 4) are warranted. In arriving at this position, the EPA has assumed that the existing processing plant's focus on producing concentrates and the proposed re-instatement of an electrowinning circuit are permissible under the terms of the existing consent.
Armidale Dumaresq Council
Comment
Armidale Dumaresq Council
Comment
Armidale
,
New South Wales
Message
I would like to advise that after reviewing the documentation submitted with the s75W modification to DA 98/00802 that Council has no specific objections to the Applicants request for an amendment of condition 4 of the Consent to modify the wording to remove any uncertainty in the date the consent would lapse.
As such, Council does not object to removing reference in the documentation to the 'Consent shall lapse 12 years after the date of commencement of substantial construction', with the wording 'The Applicant may carry out mining operations on the site in accordance with the consent until 31 December 2019'.
Regards
John Goodall
Manager Development Assessment | Planning & Environment Division
As such, Council does not object to removing reference in the documentation to the 'Consent shall lapse 12 years after the date of commencement of substantial construction', with the wording 'The Applicant may carry out mining operations on the site in accordance with the consent until 31 December 2019'.
Regards
John Goodall
Manager Development Assessment | Planning & Environment Division
RMS
Comment
RMS
Comment
Office of Environment and Heritage
Comment
Office of Environment and Heritage
Comment
Division of Resources and Energy
Comment
Division of Resources and Energy
Comment
Hunter Region MC
,
New South Wales
Message
See attachment
Attachments
Department of Primary Industries
Comment
Department of Primary Industries
Comment
Sydney
,
New South Wales
Message
See attached.
Attachments
Pagination
Project Details
Application Number
DA98/35-Mod-3
Main Project
DA98/35
Assessment Type
Part3A Modifications
Development Type
Minerals Mining
Local Government Areas
Armidale Regional
Decision
Approved
Determination Date
Decider
IPC-N
Related Projects
DA98/35-Mod-3
Determination
Part3A Modifications
Mod 3 - Extension of Mine Life
130 Brackin Street Hillgrove New South Wales Australia 2530
DA98/35-Mod-4
Determination
Part3A Modifications
Mod 4 - Administrative Change
130 Brackin Street Hillgrove New South Wales Australia 2530
DA98/35-Mod-2
Determination
Part4Mod
Mod 2 - Administrative Change
130 Brackin Street, ,Hillgrove,New South Wales,2530,Australia
DA98/35-Mod-1
Determination
Part4Mod
Mod 1 - Administrative Change
130 Brackin Street, ,Hillgrove,New South Wales,2530,Australia
DA98/35-Mod-5
Prepare Mod Report
SSD Modifications
Mod 5 – Extension of Mine Life
130 Brackin Street, ,Hillgrove,New South Wales,2530,Australia