Name Withheld
Object
Kings Point , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Name Withheld
Object
Bruce , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.
The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's lack of community consultation.
AGL have not supplied adequate time for an appropriate response.
AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.
This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.
The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.
AGL would appear to be pursuing a flawed and obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.
Finally the construction of this power plant will potentially close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.
Thank you
Name Withheld
Object
Bywong , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW on these grounds:

AGL has not provided sufficient cause for an extension.

The community distrusts AGL as acknowledged by the Department of Planning.

AGL has not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is seven years old and, I'm told, does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less a few kilometres from the proposed construction.

Proposed modifications mean this is now a new proposal that requires a new assessment. AGL received its original approval under legislation repealed in 2011. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL has been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority that does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that, in two years' time, a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL appears to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be uneconomic. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince and Janet Heffernan at "Moorlands" Dalton who supply me and my family with lamb. I object to this loss and this destruction of their business.
Name Withheld
Object
Watson , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.
The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.
AGL have not supplied adequate time for an appropriate response.
AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.
This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.
The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.
AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.
Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.
Thank you


Name Withheld
Object
Hurlstone Park , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you

Name Withheld
Object
Kaleen , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Name Withheld
Object
CHISHOLM , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.
The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.
AGL have not supplied adequate time for an appropriate response.
AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.
This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.
The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.
AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.
Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.
Thank you
Name Withheld
Object
Deakin act , Australian Capital Territory
Message
A pollying short term solution that should not be allowed to occur
Louisa Casino
Object
Woodford , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Louisa Casino
Jennifer Pickard
Object
Fisher , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

AGL have not supplied adequate time for an appropriate response and consequently, distrust has arisen. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

Other technologies are far more appropriate and worth considering from a sustainable and financial perspective. AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.
Marilyn Irons
Object
North Narrabeen , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.
The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.
AGL have not supplied adequate time for an appropriate response.
AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.
This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.
The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.
AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.
Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.
Thank you
elijah pope
Object
nelly bay , Queensland
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Cathy Temple
Object
Terrey Hills , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
miguel casino
Object
Penrith , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Tania Klein
Object
North Ward, Townsville , Queensland
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Tania Klein
Object
North Ward, Townsville , Queensland
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
Name Withheld
Object
Cook , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you,
Linda Jones
Object
Kambah , Australian Capital Territory
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.
Julie Korowe
Object
RIVERVIEW , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you
STEVEN KOROWE
Object
RIVERVIEW , New South Wales
Message
I wish to lodge my objection to AGL's proposed extension of time for the commencement of work on the proposed gas fired power plant project at Dalton (DPP), NSW. AGL have not provided sufficient cause for extension.

The community distrusts them. This has been acknowledged by the Department of Planning who noted AGL's appalling community consultation.

AGL have not supplied adequate time for an appropriate response.

AGL will rely on an Environmental Assessment that is 7 years old and does not include recent discoveries including the population of endangered Southern Pygmy Perch in Oolong Creek less than a few kilometres from the proposed construction.

This is a new proposal and needs a new assessment. AGL received its original approval under legislation repealed in 2011 after a corruption scandal that brought down the then NSW government. By repealing this legislation, the NSW Government acknowledged corrupt and unfair practices, such as undisclosed political donations made during the assessment of the original Dalton proposal and for which AGL have been convicted and fined. Hence it may be argued that the original assessment and approval were made under a defective head of authority which does not provide a legitimate basis for the project.

The rate of development of battery and alternative generating technologies is such that in two years' time a gas-fired generator may well be obsolete and, if built, a stranded asset.

AGL would appear to be pursuing a flawed and obsolescent if not obsolete business model. The whole-of-life cost of this project to the government and citizens of NSW may be an impediment to growth in this state. This proposed development is at odds with the electricity market now and in the future.

Finally the construction of this power plant will close down the business of Vince & Janet Heffernan at "Moorlands" Dalton who supply me and my family lamb. I object to this loss and this destruction of their business.

Thank you

Pagination

Project Details

Application Number
MP10_0035-Mod-1
Main Project
MP10_0035
Assessment Type
Part3A Modifications
Development Type
Electricity generation - Other
Local Government Areas
Upper Lachlan Shire

Contact Planner

Name
Anthony Ko