FRNSW has no objection to the proposal regarding the demolition and
reconstruction of the SFS. FRNSW is in consultation with
Infrastructure NSW regarding the new stadium and understands that this
consultation will continue as plans are developed.
In relation to the demolition and construction phase of the
development FRNSW notes that the driveway on the eastern side of the
SFS has booster facilities for the fire services, fire hydrant and
sprinkler systems, that service the SCG. The driveway also provides
access for fire-fighters to the SCG in the instance of a fire or other
emergency at the SCG. Access is to be maintained during demolition and
construction of the SFS to these booster facilities and to the SCG via
this driveway. If access is to be restricted or blocked to these
booster facilities or to the SCG via this driveway, for any period of
time during the demolition and construction of the SFS, it requested
that FRNSW be advised in writing two (2) days prior to the access
being restricted, so that operational plans can be put in place whilst
access is restricted.
The written advice is to be forwarded to the following email addresses
of FRNSW:
*
[email protected]
*
[email protected]
*
[email protected]
Again apologies for the delay in getting this to you. Please do not
hesitate to contact me should you require any further advice regarding
this matter.