State Significant Development
Determination
Horsely Park Business - Lot 3 Warehouse Facility
Fairfield
Current Status: Determination
Interact with the stages for their names
- SEARs
- Prepare EIS
- Exhibition
- Collate Submissions
- Response to Submissions
- Assessment
- Recommendation
- Determination
Modifications
Determination
Archive
Application (2)
Request for DGRS (2)
DGRs (2)
EIS (41)
Response to Submissions (12)
Determination (3)
Approved Documents
There are no post approval documents available
Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.
Complaints
Want to lodge a compliance complaint about this project?
Make a ComplaintEnforcements
There are no enforcements for this project.
Inspections
There are no inspections for this project.
Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.
Submissions
Showing 1 - 10 of 10 submissions
Transport for NSW
Comment
Transport for NSW
Comment
Haymarket
,
New South Wales
Message
See attached
Attachments
Endeavour Energy
Comment
Endeavour Energy
Comment
Seven Hills
,
New South Wales
Message
See attached
Attachments
OEH Heritage Council of NSW
Comment
OEH Heritage Council of NSW
Comment
Parramatta
,
New South Wales
Message
See attached
Attachments
Fairfield City Council
Comment
Fairfield City Council
Comment
Wakeley
,
New South Wales
Message
OVERVIEW
The development application seeks approval for a proposed warehouse/industrial facility on the subject site at Lot 3, Horsley Drive Business Park, Horsley Park. The proposal seeks approval for two warehouses:
Warehouse/Industrial facility 1 includes a 13,690m2 warehouse/industrial facility, 500m2 office mezzanine, and
100 parking spaces.
Warehouse/Industrial facility 2 includes a 8,690m2 warehouse/industrial facility, 500m2 office mezzanine, and
59 parking spaces.
The following comment is provided to the proposal.
STORMWATER DRAINAGE
The Civil Design Report prepared by Costin Roe and advises how the stormwater generated from this development will discharge into the existing drainage system including summarising and explaining the stormwater issues related to the site.
Council's position has always been that stormwater generated from a development should be managed within its boundaries. The Concept approval included an off-lot detention basin and bio-retention basin, which is contrary to Council's stormwater and OSD policy, therefore no comments are provided with regard to discharge of the generated stormwater.
Extract Civil Design Report cites `In terms of stormwater measures, it is proposed to discharge the site drainage to the existing and approved connection point located at the North East corner of the site. The approved subdivision drawings Co11492.05-C41-C48 show this connection point and how the site fits with the overall subdivision stormwater strategy. After the site discharges into the approved and existing connection stub, it will be directed to the existing Detention and Water Quality Basin. This basin has been designed to accommodate this site's water quality and detention requirements. The subdivision report prepared by Costin Roe titled Civil Engineering Report - Horsley Drive Business Park, S96 Application (Rev A December 2014) details the stormwater strategy for Detention and Water Quality.' The internal drainage system has been designed to cater for the 100 Year ARI, with safe overland flow routes in the event of a total system failure. A 300mm freeboard above the overflow spill level has been provided for the proposed FFL which is acceptable. The external catchments will be intercepted and diverted via a swale/channel and 750mm pipe and then directed to the existing overland flow channel to the north of the site. This was a previously approved concept. As such, Council raises no objection in this regard.
ROADS AND TRAFFIC
There will be conflict between B-Doubles servicing warehouse 1 and warehouse 2 at the entry/exit of warehouse 2. Information should be provided on how the conflict will be managed.
The proposed driveway width for cars is 5.5m at the site boundary. As this driveway will be servicing one hundred and fifty nine (159) parking spaces, under the provision of AS/NZS 2890.1:2004, the minimum width of the driveway required is 6m.
Your consideration of matters raised is appreciated.
The development application seeks approval for a proposed warehouse/industrial facility on the subject site at Lot 3, Horsley Drive Business Park, Horsley Park. The proposal seeks approval for two warehouses:
Warehouse/Industrial facility 1 includes a 13,690m2 warehouse/industrial facility, 500m2 office mezzanine, and
100 parking spaces.
Warehouse/Industrial facility 2 includes a 8,690m2 warehouse/industrial facility, 500m2 office mezzanine, and
59 parking spaces.
The following comment is provided to the proposal.
STORMWATER DRAINAGE
The Civil Design Report prepared by Costin Roe and advises how the stormwater generated from this development will discharge into the existing drainage system including summarising and explaining the stormwater issues related to the site.
Council's position has always been that stormwater generated from a development should be managed within its boundaries. The Concept approval included an off-lot detention basin and bio-retention basin, which is contrary to Council's stormwater and OSD policy, therefore no comments are provided with regard to discharge of the generated stormwater.
Extract Civil Design Report cites `In terms of stormwater measures, it is proposed to discharge the site drainage to the existing and approved connection point located at the North East corner of the site. The approved subdivision drawings Co11492.05-C41-C48 show this connection point and how the site fits with the overall subdivision stormwater strategy. After the site discharges into the approved and existing connection stub, it will be directed to the existing Detention and Water Quality Basin. This basin has been designed to accommodate this site's water quality and detention requirements. The subdivision report prepared by Costin Roe titled Civil Engineering Report - Horsley Drive Business Park, S96 Application (Rev A December 2014) details the stormwater strategy for Detention and Water Quality.' The internal drainage system has been designed to cater for the 100 Year ARI, with safe overland flow routes in the event of a total system failure. A 300mm freeboard above the overflow spill level has been provided for the proposed FFL which is acceptable. The external catchments will be intercepted and diverted via a swale/channel and 750mm pipe and then directed to the existing overland flow channel to the north of the site. This was a previously approved concept. As such, Council raises no objection in this regard.
ROADS AND TRAFFIC
There will be conflict between B-Doubles servicing warehouse 1 and warehouse 2 at the entry/exit of warehouse 2. Information should be provided on how the conflict will be managed.
The proposed driveway width for cars is 5.5m at the site boundary. As this driveway will be servicing one hundred and fifty nine (159) parking spaces, under the provision of AS/NZS 2890.1:2004, the minimum width of the driveway required is 6m.
Your consideration of matters raised is appreciated.
Attachments
RMS
Comment
RMS
Comment
Department of Primary Industries
Comment
Department of Primary Industries
Comment
Sydney
,
New South Wales
Message
See attached
Attachments
DPI - Division of Resources & Energy
Comment
DPI - Division of Resources & Energy
Comment
Hunter Regional Mail Centre
,
New South Wales
Message
See attached
Attachments
WaterNSW
Comment
WaterNSW
Comment
Penrith
,
New South Wales
Message
See Attached
Attachments
Syndey Water
Comment
Syndey Water
Comment
Parramatta
,
New South Wales
Message
See attached
Attachments
Transgrid
Comment
Transgrid
Comment
Sydney
,
New South Wales
Message
See attached
Attachments
Pagination
Project Details
Application Number
SSD-7917
Assessment Type
State Significant Development
Development Type
Warehouse or distribution centres
Local Government Areas
Fairfield
Decision
Approved
Determination Date
Decider
ED
Last Modified By
SSD-7917-MOD-1
Last Modified On
09/08/2017
Contact Planner
Name
Thomas
Piovesan
Related Projects
SSD-7917-MOD-1
Determination
SSD Modifications
Mod 1
Corner Of The Horsley Drive &Amp; Cowpasture Road Wetherill Park New South Wales Australia